Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
794
matching recommendationsSIC | 2869 | Industrial Organic Chemicals, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CC0037 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,523 | $8,400 | n/a |
CC0037 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,159 | $1,880 | n/a |
CC0037 # 09 Y:2024 | 09 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,257 | $183,891 | n/a |
CC0037 # 08 Y:2024 | 08 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $2,800 | $0 | n/a |
CC0037 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $11,158 | $17,000 | n/a |
CC0037 # 06 Y:2024 | 06 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,010 | $2,500 | n/a |
CC0037 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,282 | $1,000 | n/a |
CC0037 # 04 Y:2024 | 04 | 2024 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,235 | $0 | n/a |
MI0441 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $58,244 | $186,000 | Implemented |
MI0441 # 02 Y:2024 | 02 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $24,362 | $840 | Not Implemented |
MI0441 # 03 Y:2024 | 03 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $21,427 | $1,306 | Implemented |
MI0441 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,377 | $510 | Implemented |
MI0441 # 05 Y:2024 | 05 | 2024 | USE SOLAR HEAT TO HEAT WATER | $2,247 | $2,602 | Not Implemented |
MI0441 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,124 | $1,980 | Implemented |
MI0441 # 07 Y:2024 | 07 | 2024 | INSTALL OCCUPANCY SENSORS | $671 | $1,203 | Implemented |
OK1093 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,678 | $10,052 | Implemented |
OK1093 # 13 Y:2023 | 13 | 2023 | MAKE A NEW BY-PRODUCT | $1,221,405 | $1,600,000 | Implemented |
OK1093 # 12 Y:2023 | 12 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $150,722 | $300,000 | Implemented |
OK1093 # 11 Y:2023 | 11 | 2023 | CHANGE METHOD OF DEIONIZED WATER PRODUCTION | $98,980 | $367,077 | Implemented |
OK1093 # 10 Y:2023 | 10 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $31,034 | $19,400 | Not Implemented |
OK1093 # 09 Y:2023 | 09 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,201 | $632 | Not Implemented |
OK1093 # 08 Y:2023 | 08 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $12,354 | $1,420 | Implemented |
OK1093 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,345 | $8,534 | Implemented |
OK1093 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,010 | $0 | Implemented |
OK1093 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,087 | $343 | Implemented |