Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
685
matching recommendationsSIC | 29 | Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0622 # 05 Y:2022 | 05 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $898 | $300 | Implemented |
LS2214 # 05 Y:2022 | 05 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $53,187 | $50,000 | Implemented |
LS2214 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $217 | $38 | Implemented |
LS2214 # 01 Y:2022 | 01 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $137 | $0 | Implemented |
LS2214 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,189 | $270 | Implemented |
AM0841 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $25,385 | $3,000 | Implemented |
AM0841 # 02 Y:2022 | 02 | 2022 | OPTIMIZE PLANT POWER FACTOR | $4,790 | $6,720 | Implemented |
AM0841 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $898 | $598 | Implemented |
AM0841 # 05 Y:2022 | 05 | 2022 | USE PHOTOCELL CONTROLS | $140 | $100 | Implemented |
OK1048 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,475 | $13,356 | Implemented |
OK1048 # 03 Y:2021 | 03 | 2021 | INSTALL OCCUPANCY SENSORS | $2,257 | $3,150 | Implemented |
OK1048 # 01 Y:2021 | 01 | 2021 | REPAIR AND ELIMINATE STEAM LEAKS | $37,041 | $2,860 | Implemented |
SD0604 # 04 Y:2020 | 04 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,562 | $3,960 | Implemented |
SD0604 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,064 | $0 | Implemented |
SD0604 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,750 | $1,200 | Implemented |
AS0488 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $2,602 | $272 | Implemented |
AS0488 # 04 Y:2020 | 04 | 2020 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,344 | $36 | Implemented |
AS0488 # 01 Y:2020 | 01 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $118,609 | $10,790 | Implemented |
AS0488 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,864 | $7,653 | Implemented |
CL1912 # 02 Y:2019 | 02 | 2019 | MINIMIZE WATER USAGE | $1,166 | $1,750 | Implemented |
SF0545 # 06 Y:2019 | 06 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,757 | $1,300,334 | Implemented |
SF0545 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,924 | $11,386 | Implemented |
CL1912 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $5,433 | $15,806 | Implemented |
CL1912 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,757 | $4,162 | Implemented |
SF0545 # 01 Y:2019 | 01 | 2019 | INSULATE BARE EQUIPMENT | $1,151 | $1,194 | Implemented |