Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
69
matching recommendationsSIC | 29 | Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1074 # 05 Y:2022 | 05 | 2022 | INSULATE BARE EQUIPMENT | $1,700 | $611 | Not Implemented |
OK1074 # 04 Y:2022 | 04 | 2022 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,213 | $895 | Implemented |
OK1074 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,000 | $2,520 | Implemented |
OK1074 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $470 | $187 | Not Implemented |
OK1074 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $362 | $0 | Not Implemented |
OK1048 # 05 Y:2021 | 05 | 2021 | OPTIMIZE PLANT POWER FACTOR | $22,294 | $15,000 | Not Implemented |
OK1048 # 04 Y:2021 | 04 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,153 | $4,000 | Not Implemented |
OK1048 # 01 Y:2021 | 01 | 2021 | REPAIR AND ELIMINATE STEAM LEAKS | $37,041 | $2,860 | Implemented |
OK1048 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,475 | $13,356 | Implemented |
OK1048 # 03 Y:2021 | 03 | 2021 | INSTALL OCCUPANCY SENSORS | $2,257 | $3,150 | Implemented |
OK1001 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $1,894 | $955 | Not Implemented |
OK1001 # 03 Y:2019 | 03 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,474 | $11,240 | Not Implemented |
OK1001 # 05 Y:2019 | 05 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,655 | $15,329 | Not Implemented |
OK1001 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,178 | $16,224 | Not Implemented |
OK1001 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,799 | $3,509 | Implemented |
OK0719 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $56,779 | $157,975 | Not Implemented |
OK0719 # 02 Y:2006 | 02 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $13,491 | $550 | Implemented |
OK0719 # 03 Y:2006 | 03 | 2006 | USE OPTIMUM THICKNESS INSULATION | $3,078 | $1,637 | Implemented |
OK0719 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $49 | $92 | Not Implemented |
OK0719 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $282 | $80 | Implemented |
OK0719 # 06 Y:2006 | 06 | 2006 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $221 | $225 | Implemented |
OK0719 # 04 Y:2006 | 04 | 2006 | INSULATE BARE EQUIPMENT | $249 | $1,098 | Not Implemented |
OK0690 # 03 Y:2004 | 03 | 2004 | INSTALL SET-BACK TIMERS | $2,316 | $400 | Implemented |
OK0690 # 04 Y:2004 | 04 | 2004 | INSTALL OCCUPANCY SENSORS | $8,325 | $800 | Implemented |
OK0690 # 05 Y:2004 | 05 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,000 | $0 | Implemented |