Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
911
matching recommendationsSIC | 295 | Asphalt Paving And Roofing Materials |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0294 # 06 Y:1997 | 06 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,133 | $3,516 | Implemented |
OR0294 # 07 Y:1997 | 07 | 1997 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $8,920 | $80,000 | Not Implemented |
OR0294 # 08 Y:1997 | 08 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $9,140 | $80,000 | Not Implemented |
OR0294 # 09 Y:1997 | 09 | 1997 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $117,450 | $206,000 | Not Implemented |
OR0294 # 10 Y:1997 | 10 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $11,700 | $22,500 | Not Implemented |
OR0294 # 11 Y:1997 | 11 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,160 | $0 | Implemented |
OR0290 # 01 Y:1997 | 01 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $7,230 | $20,000 | Not Implemented |
OR0290 # 02 Y:1997 | 02 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,870 | $5,000 | Not Implemented |
OR0290 # 03 Y:1997 | 03 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $349 | $2,216 | Implemented |
OR0290 # 04 Y:1997 | 04 | 1997 | RECOVER AND REUSE WASTE MATERIAL | $27,000 | $260,000 | Not Implemented |
UD0493 # 01 Y:1996 | 01 | 1996 | KEEP BOILER TUBES CLEAN | $2,375 | $500 | Implemented |
UD0493 # 02 Y:1996 | 02 | 1996 | REPAIR OR REPLACE STEAM TRAPS | $10,368 | $9,000 | Implemented |
UD0493 # 03 Y:1996 | 03 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,952 | $2,500 | Implemented |
UD0493 # 04 Y:1996 | 04 | 1996 | USE PHOTOCELL CONTROLS | $1,741 | $1,375 | Implemented |
UD0493 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,907 | $15,000 | Implemented |
UD0493 # 06 Y:1996 | 06 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,431 | $5,975 | Implemented |
UD0493 # 07 Y:1996 | 07 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,554 | $5,953 | Implemented |
UD0493 # 08 Y:1996 | 08 | 1996 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $11,264 | $45,000 | Not Implemented |
UD0493 # 09 Y:1996 | 09 | 1996 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $14,773 | $34,000 | Implemented |
OK0492 # 01 Y:1996 | 01 | 1996 | INSULATE BARE EQUIPMENT | $2,709 | $3,419 | Implemented |
OK0492 # 02 Y:1996 | 02 | 1996 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,502 | $500 | Implemented |
OK0492 # 03 Y:1996 | 03 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $522 | $468 | Not Implemented |
OK0492 # 04 Y:1996 | 04 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,800 | $0 | Implemented |
AR0065 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $999 | $410 | Implemented |
AR0065 # 02 Y:1995 | 02 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $761 | $420 | Implemented |