Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
411
matching recommendationsSIC | 2951 | Asphalt Paving Mixtures And Blocks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0249 # 03 Y:2025 | 03 | 2025 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,075 | $1,777 | n/a |
DL0249 # 01 Y:2025 | 01 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $43,100 | $30,000 | n/a |
DL0249 # 05 Y:2025 | 05 | 2025 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,172 | $13,000 | n/a |
DL0249 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,102 | $10,000 | n/a |
DL0249 # 08 Y:2025 | 08 | 2025 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $5,230 | $38,000 | n/a |
DL0249 # 07 Y:2025 | 07 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $7,174 | $15,000 | n/a |
DL0249 # 06 Y:2025 | 06 | 2025 | INSULATE BARE EQUIPMENT | $35,225 | $8,950 | n/a |
DL0249 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,975 | $20,000 | n/a |
IC0301 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,209 | $186,605 | n/a |
IC0301 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,487 | $0 | n/a |
IC0301 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,042 | $205 | n/a |
IC0301 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,652 | $0 | n/a |
IC0301 # 08 Y:2024 | 08 | 2024 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $2,673 | $890 | n/a |
IC0301 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,886 | $205 | n/a |
IC0301 # 07 Y:2024 | 07 | 2024 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $13,766 | $3,820 | n/a |
IC0301 # 02 Y:2024 | 02 | 2024 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $26,388 | $3,600 | n/a |
UF0605 # 05 Y:2023 | 05 | 2023 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,444,605 | $0 | Implemented |
UF0605 # 02 Y:2023 | 02 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $38,052 | $10,000 | Implemented |
UF0605 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $108,422 | $322,608 | Not Implemented |
UF0605 # 06 Y:2023 | 06 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $5,654 | $20,000 | Implemented |
UF0605 # 03 Y:2023 | 03 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,825 | $11,200 | Implemented |
UF0605 # 04 Y:2023 | 04 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $3,043 | $2,800 | Implemented |
UA0280 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,338 | $353 | n/a |
UA0280 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,472 | $1,000 | n/a |
UA0280 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,180 | $3,163 | n/a |