Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
411
matching recommendationsSIC | 2951 | Asphalt Paving Mixtures And Blocks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0280 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,338 | $353 | n/a |
UA0269 # 02 Y:2023 | 02 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $21,248 | $98,929 | Not Implemented |
UA0269 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,634 | $842 | Not Implemented |
UA0269 # 06 Y:2023 | 06 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $2,642 | $297 | Not Implemented |
UA0269 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,902 | $3,140 | Not Implemented |
UA0269 # 01 Y:2023 | 01 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $147,247 | $186,762 | Not Implemented |
UA0269 # 07 Y:2023 | 07 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $751 | $251 | Not Implemented |
UA0269 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $2,019 | $2,438 | Not Implemented |
LS2214 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $226 | $25 | Not Implemented |
LS2214 # 07 Y:2022 | 07 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $63 | $150 | Not Implemented |
LS2214 # 05 Y:2022 | 05 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $53,187 | $50,000 | Implemented |
LS2214 # 01 Y:2022 | 01 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $137 | $0 | Implemented |
LS2214 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,374 | $1,394 | Not Implemented |
LS2214 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,189 | $270 | Implemented |
LS2214 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $217 | $38 | Implemented |
AS0488 # 01 Y:2020 | 01 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $118,609 | $10,790 | Implemented |
AS0488 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,944 | $27,312 | Not Implemented |
AS0488 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $2,602 | $272 | Implemented |
AS0488 # 04 Y:2020 | 04 | 2020 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,344 | $36 | Implemented |
AS0488 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,864 | $7,653 | Implemented |
AS0488 # 06 Y:2020 | 06 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,828 | $3,940 | Not Implemented |
AS0488 # 07 Y:2020 | 07 | 2020 | INSTALL OCCUPANCY SENSORS | $395 | $1,840 | Not Implemented |
SF0545 # 05 Y:2019 | 05 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,742 | $17,476 | Not Implemented |
SF0545 # 06 Y:2019 | 06 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,757 | $1,300,334 | Implemented |
CL1912 # 04 Y:2019 | 04 | 2019 | PAY UTILITY BILLS ON TIME | $103 | $0 | Implemented |