Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 2952 | Asphalt Felts And Coatings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LM0111 # 06 Y:2006 | 06 | 2006 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $650,132 | $0 | Implemented |
LM0111 # 05 Y:2006 | 05 | 2006 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $235,359 | $7,000 | Not Implemented |
LM0111 # 04 Y:2006 | 04 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,249 | $522 | Not Implemented |
LM0111 # 03 Y:2006 | 03 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $879 | $5,000 | Implemented |
LM0111 # 01 Y:2006 | 01 | 2006 | USE OPTIMUM TEMPERATURE | $1,018 | $0 | Not Implemented |
LM0111 # 02 Y:2006 | 02 | 2006 | INSULATE BARE EQUIPMENT | $2,109 | $3,000 | Implemented |
OK0719 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $49 | $92 | Not Implemented |
OK0719 # 06 Y:2006 | 06 | 2006 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $221 | $225 | Implemented |
OK0719 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $282 | $80 | Implemented |
OK0719 # 04 Y:2006 | 04 | 2006 | INSULATE BARE EQUIPMENT | $249 | $1,098 | Not Implemented |
OK0719 # 03 Y:2006 | 03 | 2006 | USE OPTIMUM THICKNESS INSULATION | $3,078 | $1,637 | Implemented |
OK0719 # 02 Y:2006 | 02 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $13,491 | $550 | Implemented |
OK0719 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $56,779 | $157,975 | Not Implemented |
CO0580 # 11 Y:2006 | 11 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $280 | $500 | Implemented |
CO0580 # 10 Y:2006 | 10 | 2006 | USE SOLAR HEAT FOR HEAT | $470 | $1,400 | Not Implemented |
CO0580 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $660 | $1,830 | Implemented |
CO0580 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $900 | $1,610 | Not Implemented |
CO0580 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $50 | $20 | Implemented |
CO0580 # 06 Y:2006 | 06 | 2006 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $1,460 | $9,360 | Not Implemented |
CO0580 # 05 Y:2006 | 05 | 2006 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $3,310 | $980 | Implemented |
CO0580 # 04 Y:2006 | 04 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,750 | $12,850 | Implemented |
CO0580 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $9,880 | $3,190 | Not Implemented |
CO0580 # 02 Y:2006 | 02 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $10,650 | $500 | Implemented |
CO0580 # 01 Y:2006 | 01 | 2006 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $479,740 | $28,080 | Not Implemented |