Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
132
matching recommendationsSIC | 2992 | Lubricating Oils And Greases |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0316 # 01 Y:1990 | 01 | 1990 | INSTALL SET-BACK TIMERS | $3,487 | $2,075 | Implemented |
KU0316 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $924 | $1,005 | Implemented |
KU0316 # 03 Y:1990 | 03 | 1990 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,122 | $15,000 | Implemented |
KU0316 # 05 Y:1990 | 05 | 1990 | OPTIMIZE PLANT POWER FACTOR | $2,160 | $2,250 | Implemented |
KU0316 # 06 Y:1990 | 06 | 1990 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,034 | $1,000 | Implemented |
KU0207 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,525 | $0 | Implemented |
KU0207 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,480 | $0 | Implemented |
KU0207 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $9,165 | $1,494 | Implemented |
KU0207 # 06 Y:1986 | 06 | 1986 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,637 | $6,030 | Implemented |
KU0207 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,817 | $52 | Implemented |
KU0207 # 09 Y:1986 | 09 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,433 | $0 | Implemented |
KU0207 # 11 Y:1986 | 11 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Implemented |
KU0207 # 12 Y:1986 | 12 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $150 | Implemented |
KU0207 # 13 Y:1986 | 13 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $469 | $0 | Implemented |
KU0207 # 14 Y:1986 | 14 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $454 | $20 | Implemented |
KU0207 # 16 Y:1986 | 16 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $128 | $100 | Implemented |
KU0207 # 17 Y:1986 | 17 | 1986 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $160 | $300 | Implemented |
OK0194 # 01 Y:1986 | 01 | 1986 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $58,564 | $35,000 | Implemented |
OK0194 # 02 Y:1986 | 02 | 1986 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $1,873 | $500 | Implemented |
OK0194 # 03 Y:1986 | 03 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $540 | $1,475 | Implemented |
OK0189 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,573 | $2,082 | Implemented |
OK0189 # 02 Y:1986 | 02 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,617 | $0 | Implemented |
OK0189 # 03 Y:1986 | 03 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $4,105 | $5,300 | Implemented |
OK0189 # 07 Y:1986 | 07 | 1986 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $986 | $2,550 | Implemented |
KU0104 # 01 Y:1983 | 01 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,312 | $1,500 | Implemented |