Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
31
matching recommendationsSIC | 2992 | Lubricating Oils And Greases |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2405 # 06 Y:2024 | 06 | 2024 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $129,015 | $600,000 | Not Implemented |
LS2405 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $155,225 | $550,000 | Implemented |
LS2405 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,207 | $25,301 | Implemented |
LS2405 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,417 | $135 | Implemented |
LS2405 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,023 | $50 | Not Implemented |
LS2405 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,278 | $0 | Implemented |
LL0275 # 08 Y:2007 | 08 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $121 | $70 | Implemented |
LL0275 # 07 Y:2007 | 07 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $386 | $200 | Not Implemented |
LL0275 # 06 Y:2007 | 06 | 2007 | INSULATE BARE EQUIPMENT | $523 | $507 | Not Implemented |
LL0275 # 05 Y:2007 | 05 | 2007 | USE PHOTOCELL CONTROLS | $1,014 | $90 | Not Implemented |
LL0275 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,791 | $690 | Implemented |
LL0275 # 03 Y:2007 | 03 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,372 | $240 | Implemented |
LL0275 # 02 Y:2007 | 02 | 2007 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $6,002 | $750 | Implemented |
LL0275 # 01 Y:2007 | 01 | 2007 | ADJUST BURNERS FOR EFFICIENT OPERATION | $9,761 | $500 | Not Implemented |
LL0172 # 09 Y:2003 | 09 | 2003 | PAY UTILITY BILLS ON TIME | $2,767 | $30 | Implemented |
LL0172 # 10 Y:2003 | 10 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,141 | $1,050 | Not Implemented |
LL0172 # 08 Y:2003 | 08 | 2003 | USE PHOTOCELL CONTROLS | $3,809 | $1,176 | Not Implemented |
LL0172 # 07 Y:2003 | 07 | 2003 | INSULATE BARE EQUIPMENT | $5,380 | $682 | Not Implemented |
LL0172 # 06 Y:2003 | 06 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $21,972 | $5,600 | Implemented |
LL0172 # 05 Y:2003 | 05 | 2003 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $65,820 | $312,701 | Not Implemented |
LL0172 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $87,485 | $28,240 | Implemented |
LL0172 # 03 Y:2003 | 03 | 2003 | INSULATE BARE EQUIPMENT | $101,833 | $7,757 | Not Implemented |
LL0172 # 02 Y:2003 | 02 | 2003 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $197,664 | $250,000 | Not Implemented |
LL0172 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $390,733 | $195,000 | Implemented |
LL0165 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $1,037,596 | $14,410 | Implemented |