Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
325
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL0170 # 01 Y:1996 | 01 | 1996 | OPTIMIZE PLANT POWER FACTOR | $6,726 | $7,330 | Implemented |
ND0265 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $386 | $527 | Implemented |
ND0265 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $232 | $360 | Implemented |
UL0170 # 04 Y:1996 | 04 | 1996 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $3,360 | $200 | Implemented |
ND0265 # 06 Y:1996 | 06 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $642 | $3,360 | Implemented |
UL0170 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $937 | $636 | Implemented |
UL0170 # 07 Y:1996 | 07 | 1996 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $1,829 | $1,500 | Implemented |
BD0074 # 12 Y:1996 | 12 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $6,360 | $6,750 | Implemented |
NV0067 # 06 Y:1996 | 06 | 1996 | OPTIMIZE PLANT POWER FACTOR | $1,021 | $0 | Implemented |
BD0074 # 13 Y:1996 | 13 | 1996 | MINIMIZE WATER USAGE | $1,210 | $500 | Implemented |
NV0067 # 07 Y:1996 | 07 | 1996 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $1,095 | $0 | Implemented |
NV0067 # 05 Y:1996 | 05 | 1996 | USE POWER DURING OFF-PEAK PERIODS | $14,885 | $0 | Implemented |
IA0158 # 03 Y:1996 | 03 | 1996 | OPTIMIZE PLANT POWER FACTOR | $27,255 | $27,255 | Implemented |
IA0158 # 04 Y:1996 | 04 | 1996 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,924 | $300 | Implemented |
BD0074 # 11 Y:1996 | 11 | 1996 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $56,426 | $1,500 | Implemented |
BD0074 # 08 Y:1996 | 08 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $863 | $522 | Implemented |
BD0074 # 06 Y:1996 | 06 | 1996 | INSTALL OCCUPANCY SENSORS | $2,522 | $1,125 | Implemented |
BD0074 # 04 Y:1996 | 04 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,328 | $580 | Implemented |
BD0074 # 03 Y:1996 | 03 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,783 | $12,980 | Implemented |
BD0074 # 02 Y:1996 | 02 | 1996 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $17,093 | $0 | Implemented |
BD0074 # 01 Y:1996 | 01 | 1996 | USE POWER DURING OFF-PEAK PERIODS | $44,073 | $2,850 | Implemented |
WV0105 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,125 | $1,564 | Implemented |
WV0105 # 08 Y:1996 | 08 | 1996 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $2,370 | $500 | Implemented |
WV0105 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $486 | $293 | Implemented |
WV0105 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,079 | $1,272 | Implemented |