Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,100
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0917 # 04 Y:2015 | 04 | 2015 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,875 | $2,000 | Implemented |
OK0917 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $689 | $577 | Implemented |
OK0917 # 06 Y:2015 | 06 | 2015 | USE OPTIMUM TEMPERATURE | $8,870 | $180 | Implemented |
SU0389 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,788 | $0 | Not Implemented |
SU0389 # 02 Y:2015 | 02 | 2015 | DISCONNECT BALLASTS | $1,418 | $0 | Not Implemented |
SU0389 # 03 Y:2015 | 03 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $516 | $0 | Implemented |
SU0389 # 04 Y:2015 | 04 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $10,554 | $3,085 | Implemented |
SU0389 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $402 | $158 | Not Implemented |
SU0389 # 06 Y:2015 | 06 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,731 | $2,974 | Implemented |
SU0389 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,064 | $2,148 | Implemented |
SU0389 # 08 Y:2015 | 08 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $119 | $123 | Implemented |
SU0389 # 09 Y:2015 | 09 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $372 | $804 | Implemented |
SU0389 # 10 Y:2015 | 10 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $257 | $1,070 | Implemented |
DL0145 # 01 Y:2015 | 01 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $48,766 | $10,000 | Not Implemented |
DL0145 # 02 Y:2015 | 02 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,440 | $0 | Implemented |
DL0145 # 03 Y:2015 | 03 | 2015 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $3,810 | $700 | Not Implemented |
DL0145 # 04 Y:2015 | 04 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,618 | $30,804 | Not Implemented |
DL0145 # 05 Y:2015 | 05 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,334 | $9,600 | Not Implemented |
DL0145 # 06 Y:2015 | 06 | 2015 | INSTALL SET-BACK TIMERS | $6,174 | $2,500 | Not Implemented |
DL0145 # 07 Y:2015 | 07 | 2015 | INSTALL TIMERS AND/OR THERMOSTATS | $3,560 | $300 | Implemented |
DL0145 # 08 Y:2015 | 08 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,831 | $40,000 | Implemented |
DL0145 # 09 Y:2015 | 09 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,074 | $64,980 | Not Implemented |
OK0916 # 01 Y:2015 | 01 | 2015 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $12,740 | $0 | Implemented |
OK0916 # 02 Y:2015 | 02 | 2015 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $16,433 | $20,074 | Not Implemented |
OK0916 # 03 Y:2015 | 03 | 2015 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $30,382 | $0 | Implemented |