Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,583
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0006 # 01 Y:1993 | 01 | 1993 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $28,390 | $64,000 | Not Implemented |
SF0006 # 02 Y:1993 | 02 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,054 | $7,585 | Implemented |
SF0006 # 03 Y:1993 | 03 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,994 | $2,625 | Implemented |
SF0006 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,646 | $8,584 | Implemented |
SF0006 # 05 Y:1993 | 05 | 1993 | INSULATE BARE EQUIPMENT | $4,602 | $1,619 | Implemented |
SF0006 # 06 Y:1993 | 06 | 1993 | INSULATE BARE EQUIPMENT | $4,237 | $4,789 | Implemented |
SF0006 # 07 Y:1993 | 07 | 1993 | INSULATE BARE EQUIPMENT | $698 | $480 | Not Implemented |
SF0005 # 01 Y:1993 | 01 | 1993 | INSULATE BARE EQUIPMENT | $1,768 | $2,956 | Not Implemented |
SF0005 # 02 Y:1993 | 02 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,726 | $2,075 | Implemented |
SF0005 # 03 Y:1993 | 03 | 1993 | INSULATE BARE EQUIPMENT | $1,271 | $1,442 | Not Implemented |
SF0005 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $815 | $670 | Implemented |
SF0005 # 05 Y:1993 | 05 | 1993 | INSTALL OCCUPANCY SENSORS | $345 | $400 | Implemented |
SF0005 # 06 Y:1993 | 06 | 1993 | INSULATE BARE EQUIPMENT | $260 | $243 | Not Implemented |
SF0005 # 07 Y:1993 | 07 | 1993 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $194 | $192 | Not Implemented |
SF0003 # 01 Y:1993 | 01 | 1993 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $655 | $192 | Implemented |
SF0003 # 02 Y:1993 | 02 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,485 | $900 | Implemented |
SF0003 # 03 Y:1993 | 03 | 1993 | USE OPTIMUM THICKNESS INSULATION | $3,546 | $4,231 | Implemented |
SF0003 # 04 Y:1993 | 04 | 1993 | INSULATE BARE EQUIPMENT | $453 | $557 | Not Implemented |
SF0003 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,118 | $3,875 | Implemented |
SF0003 # 06 Y:1993 | 06 | 1993 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,294 | $14,000 | Implemented |
SD0055 # 01 Y:1993 | 01 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,575 | $1,822 | Implemented |
SD0055 # 02 Y:1993 | 02 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $2,135 | $300 | Implemented |
SD0055 # 03 Y:1993 | 03 | 1993 | SCHEDULE USE OF ELEVATORS TO CONSERVE ENERGY | $4,262 | $236 | Not Implemented |
SD0055 # 04 Y:1993 | 04 | 1993 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,447 | $0 | Not Implemented |
SD0055 # 05 Y:1993 | 05 | 1993 | INSULATE BARE EQUIPMENT | $152 | $56 | Implemented |