Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
517
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0327 # 01 Y:2025 | 01 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,321 | $0 | n/a |
TT0327 # 05 Y:2025 | 05 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $39,392 | $20,000 | n/a |
TT0327 # 03 Y:2025 | 03 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $998 | $120 | n/a |
TT0327 # 09 Y:2025 | 09 | 2025 | USE SOLAR HEAT FOR HEAT | $66,246 | $798,795 | n/a |
TT0327 # 07 Y:2025 | 07 | 2025 | INITIATE A PROGRAM TO ACQUIRE ISO CERTIFICATION | $17,852 | $35,000 | n/a |
TT0327 # 08 Y:2025 | 08 | 2025 | OPTIMIZE PLANT POWER FACTOR | $8,101 | $31,875 | n/a |
TT0327 # 04 Y:2025 | 04 | 2025 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,500 | $550 | n/a |
TT0327 # 02 Y:2025 | 02 | 2025 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,048 | $0 | n/a |
TT0327 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,254 | $1,491 | n/a |
TT0330 # 09 Y:2025 | 09 | 2025 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,928 | $11,800 | n/a |
TT0330 # 02 Y:2025 | 02 | 2025 | INSTALL OCCUPANCY SENSORS | $30,472 | $17,136 | n/a |
TT0330 # 07 Y:2025 | 07 | 2025 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $6,469 | $25,000 | n/a |
TT0330 # 04 Y:2025 | 04 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,725 | $12,000 | n/a |
TT0330 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $25,346 | $1,500 | n/a |
TT0330 # 12 Y:2025 | 12 | 2025 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $529 | $1,344 | n/a |
TT0330 # 05 Y:2025 | 05 | 2025 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,614 | $38,380 | n/a |
TT0330 # 10 Y:2025 | 10 | 2025 | INCREASE AMOUNT OF CONDENSATE RETURNED | $928 | $5,000 | n/a |
TT0330 # 11 Y:2025 | 11 | 2025 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $642 | $1,400 | n/a |
TT0330 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $508,143 | $2,436,747 | n/a |
TT0330 # 06 Y:2025 | 06 | 2025 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $10,702 | $50,000 | n/a |
TT0330 # 08 Y:2025 | 08 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,319 | $3,400 | n/a |
TT0317 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,299 | $16,125 | n/a |
TT0317 # 11 Y:2024 | 11 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $22,558 | $39,000 | n/a |
TT0317 # 03 Y:2024 | 03 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $859 | $400 | n/a |
TT0317 # 01 Y:2024 | 01 | 2024 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $374,993 | $42,000 | n/a |