Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
77
matching recommendationsSIC | 305 | Hose & Belting & Gaskets & Packing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0305 # 07 Y:2004 | 07 | 2004 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $320 | $58 | Implemented |
NC0265 # 04 Y:2003 | 04 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,206 | $1,100 | Not Implemented |
NC0265 # 03 Y:2003 | 03 | 2003 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $7,348 | $3,525 | Implemented |
NC0265 # 02 Y:2003 | 02 | 2003 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $13,226 | $24,506 | Implemented |
NC0265 # 01 Y:2003 | 01 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,793 | $7,000 | Implemented |
NC0265 # 05 Y:2003 | 05 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $7,094 | $1,000 | Implemented |
NC0265 # 06 Y:2003 | 06 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,361 | $0 | Implemented |
NC0265 # 07 Y:2003 | 07 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,469 | $300 | Implemented |
NC0265 # 08 Y:2003 | 08 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $214 | $50 | Implemented |
NC0265 # 09 Y:2003 | 09 | 2003 | INSTALL OCCUPANCY SENSORS | $100 | $89 | Implemented |
NC0029 # 01 Y:1994 | 01 | 1994 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $11,457 | $153,000 | Not Implemented |
NC0029 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,131 | $480 | Implemented |
NC0029 # 03 Y:1994 | 03 | 1994 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $14,345 | $40,000 | Implemented |
NC0029 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,050 | $520 | Not Implemented |
NC0029 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $562 | $378 | Not Implemented |
TN0336 # 07 Y:1988 | 07 | 1988 | INSULATE BARE EQUIPMENT | $418 | $274 | Not Implemented |
TN0336 # 01 Y:1988 | 01 | 1988 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $7,226 | $19,980 | Not Implemented |
TN0336 # 02 Y:1988 | 02 | 1988 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,139 | $7,500 | Implemented |
TN0336 # 03 Y:1988 | 03 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,260 | $830 | Implemented |
TN0336 # 04 Y:1988 | 04 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,494 | $0 | Implemented |
TN0336 # 05 Y:1988 | 05 | 1988 | ADJUST VENTS TO MINIMIZE ENERGY USE | $890 | $1,140 | Implemented |
TN0336 # 06 Y:1988 | 06 | 1988 | IMPROVE LUBRICATION PRACTICES | $795 | $1,650 | Not Implemented |
TN0336 # 08 Y:1988 | 08 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $189 | $180 | Implemented |
AT0064 # 04 Y:1987 | 04 | 1987 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,374 | $4,200 | Not Implemented |
AT0064 # 03 Y:1987 | 03 | 1987 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,391 | $3,000 | Not Implemented |