Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,181
matching recommendationsSIC | 305 | Hose & Belting & Gaskets & Packing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0043 # 02 Y:1994 | 02 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,021 | $6,120 | Not Implemented |
WV0043 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $787 | $500 | Implemented |
WV0043 # 04 Y:1994 | 04 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $399 | $372 | Not Implemented |
WV0043 # 05 Y:1994 | 05 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,644 | $100 | Implemented |
WV0043 # 06 Y:1994 | 06 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,788 | $530 | Not Implemented |
WV0043 # 07 Y:1994 | 07 | 1994 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $9,680 | $6,985 | Not Implemented |
NC0029 # 01 Y:1994 | 01 | 1994 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $11,457 | $153,000 | Not Implemented |
NC0029 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,131 | $480 | Implemented |
NC0029 # 03 Y:1994 | 03 | 1994 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $14,345 | $40,000 | Implemented |
NC0029 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,050 | $520 | Not Implemented |
NC0029 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $562 | $378 | Not Implemented |
OD0004 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,341 | $800 | Implemented |
OD0004 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,431 | $11,417 | Implemented |
OD0004 # 03 Y:1994 | 03 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $2,461 | $780 | Not Implemented |
OD0004 # 04 Y:1994 | 04 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $424 | $548 | Not Implemented |
GT0525 # 01 Y:1994 | 01 | 1994 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $6,630 | $5,000 | Not Implemented |
GT0525 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,470 | $6,520 | Implemented |
GT0525 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,860 | $1,150 | Implemented |
GT0525 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,170 | $32,530 | Implemented |
GT0525 # 05 Y:1994 | 05 | 1994 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $7,600 | $2,550 | Not Implemented |
GT0525 # 06 Y:1994 | 06 | 1994 | COVER OPEN TANKS | $2,280 | $740 | Not Implemented |
MA0302 # 01 Y:1994 | 01 | 1994 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $19,139 | $8,246 | Not Implemented |
MA0302 # 02 Y:1994 | 02 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,102 | $180 | Implemented |
MA0302 # 03 Y:1994 | 03 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $8,142 | $25,365 | Not Implemented |
MA0302 # 04 Y:1994 | 04 | 1994 | BURN A LESS EXPENSIVE GRADE OF FUEL | $9,629 | $17,304 | Implemented |