Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
50
matching recommendationsSIC | 305 | Hose & Belting & Gaskets & Packing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0101 # 01 Y:2012 | 01 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,105 | $1,160 | Implemented |
MZ0101 # 02 Y:2012 | 02 | 2012 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $934 | $4,969 | Not Implemented |
MZ0101 # 05 Y:2012 | 05 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $290 | $360 | Implemented |
MZ0101 # 04 Y:2012 | 04 | 2012 | INSULATE BARE EQUIPMENT | $199 | $297 | Implemented |
MZ0101 # 03 Y:2012 | 03 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,340 | $8,800 | Implemented |
MZ0034 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,188 | $32,000 | Implemented |
MZ0034 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $625 | $650 | Implemented |
MZ0034 # 07 Y:2009 | 07 | 2009 | USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS | $13,376 | $20,000 | Implemented |
MZ0034 # 01 Y:2009 | 01 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $14,217 | $1,000 | Implemented |
MZ0034 # 05 Y:2009 | 05 | 2009 | INSTALL OCCUPANCY SENSORS | $5,200 | $532 | Implemented |
MZ0034 # 03 Y:2009 | 03 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,996 | $0 | Implemented |
MZ0034 # 06 Y:2009 | 06 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $39,780 | $3,000 | Not Implemented |
MZ0033 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $169 | $178 | Implemented |
MZ0033 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,040 | $46,900 | Implemented |
MZ0033 # 01 Y:2009 | 01 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,783 | $990 | Not Implemented |
MZ0033 # 04 Y:2009 | 04 | 2009 | INSTALL OCCUPANCY SENSORS | $259 | $178 | Implemented |
MZ0033 # 05 Y:2009 | 05 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,936 | $400 | Implemented |
MZ0033 # 06 Y:2009 | 06 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,579 | $8,000 | Not Implemented |
MO0132 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,612 | $2,530 | Implemented |
MO0132 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,750 | $675 | Implemented |
MO0132 # 01 Y:1994 | 01 | 1994 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $5,780 | $1,580 | Implemented |
MO0132 # 08 Y:1994 | 08 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,412 | $490 | Implemented |
MO0132 # 09 Y:1994 | 09 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $938 | $2,385 | Not Implemented |
MO0132 # 10 Y:1994 | 10 | 1994 | USE SYNTHETIC LUBRICANT | $733 | $208 | Implemented |
MO0132 # 11 Y:1994 | 11 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $636 | $1,195 | Implemented |