Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
25
matching recommendationsSIC | 306 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0191 # 08 Y:2018 | 08 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,092 | $2,256 | Not Implemented |
UA0191 # 07 Y:2018 | 07 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $489 | $2,112 | Not Implemented |
UA0191 # 06 Y:2018 | 06 | 2018 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,997 | $0 | Implemented |
UA0191 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,391 | $150 | Not Implemented |
UA0191 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,326 | $2,165 | Implemented |
UA0191 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,060 | $34,939 | Not Implemented |
UA0191 # 02 Y:2018 | 02 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $15,914 | $0 | Implemented |
UA0191 # 01 Y:2018 | 01 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $18,889 | $37,420 | Not Implemented |
UA0024 # 05 Y:2008 | 05 | 2008 | REPAIR AND ELIMINATE STEAM LEAKS | $6,203 | $300 | Implemented |
UA0024 # 09 Y:2008 | 09 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $42,744 | $45,700 | Not Implemented |
UA0024 # 08 Y:2008 | 08 | 2008 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $24,566 | $23,000 | Not Implemented |
UA0024 # 07 Y:2008 | 07 | 2008 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $98,000 | $126,000 | Not Implemented |
UA0024 # 06 Y:2008 | 06 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,555 | $2,415 | Implemented |
UA0024 # 04 Y:2008 | 04 | 2008 | DISCONNECT BALLASTS | $1,392 | $243 | Implemented |
UA0024 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,199 | $14,155 | Not Implemented |
UA0024 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,878 | $1,500 | Implemented |
UA0024 # 01 Y:2008 | 01 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,342 | $0 | Implemented |
GT0479 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,282 | $18,910 | Not Implemented |
GT0479 # 08 Y:1992 | 08 | 1992 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $88,450 | $133,000 | Not Implemented |
GT0479 # 07 Y:1992 | 07 | 1992 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,392 | $1,250 | Not Implemented |
GT0479 # 06 Y:1992 | 06 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $17,000 | $450 | Not Implemented |
GT0479 # 05 Y:1992 | 05 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,086 | $450 | Not Implemented |
GT0479 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,378 | $28,850 | Not Implemented |
GT0479 # 03 Y:1992 | 03 | 1992 | INSULATE BARE EQUIPMENT | $16,146 | $20,488 | Not Implemented |
GT0479 # 02 Y:1992 | 02 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $2,180 | $1,480 | Not Implemented |