Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
60
matching recommendationsSIC | 306 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2402 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,943 | $1,040 | n/a |
UC2402 # 03 Y:2024 | 03 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,298 | $3,327 | n/a |
UC2402 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $7,849 | $31,027 | n/a |
UC2402 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,049 | $134,289 | n/a |
UC2402 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,261 | $150 | n/a |
UC2402 # 09 Y:2024 | 09 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $6,701 | $64,088 | n/a |
UC2402 # 06 Y:2024 | 06 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,612 | $30 | n/a |
UC2402 # 08 Y:2024 | 08 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,934 | $155 | n/a |
UC2402 # 07 Y:2024 | 07 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $419 | $1,300 | n/a |
MA0438 # 02 Y:1999 | 02 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,856 | $4,925 | Not Implemented |
MA0438 # 01 Y:1999 | 01 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,011 | $6,075 | Not Implemented |
MA0438 # 03 Y:1999 | 03 | 1999 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $1,055 | $3,400 | Not Implemented |
MA0436 # 03 Y:1999 | 03 | 1999 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $7,745 | $12,435 | Implemented |
MA0436 # 01 Y:1999 | 01 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $35,895 | $41,600 | Not Implemented |
MA0436 # 02 Y:1999 | 02 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,170 | $27,774 | Implemented |
MA0436 # 07 Y:1999 | 07 | 1999 | DISCONNECT BALLASTS | $60 | $100 | Implemented |
MA0436 # 04 Y:1999 | 04 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $15,831 | $44,552 | Not Implemented |
MA0436 # 05 Y:1999 | 05 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $16,698 | $75,790 | Not Implemented |
MA0436 # 06 Y:1999 | 06 | 1999 | INSTALL OCCUPANCY SENSORS | $148 | $77 | Implemented |
MA0335 # 02 Y:1995 | 02 | 1995 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,479 | $3,771 | Not Implemented |
MA0335 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,352 | $1,790 | Implemented |
MA0335 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $449 | $898 | Not Implemented |
MA0335 # 08 Y:1995 | 08 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $318 | $0 | Implemented |
MA0335 # 07 Y:1995 | 07 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $370 | $0 | Not Implemented |
MA0335 # 09 Y:1995 | 09 | 1995 | COMBINE UTILITY METERS | $300 | $0 | Implemented |