Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
738
matching recommendationsSIC | 3069 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0114 # 02 Y:1984 | 02 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,818 | $900 | Implemented |
UD0114 # 04 Y:1984 | 04 | 1984 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $2,038 | $4,000 | Implemented |
UD0114 # 05 Y:1984 | 05 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $7,377 | $33,750 | Implemented |
UD0114 # 06 Y:1984 | 06 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,899 | $0 | Implemented |
OK0094 # 04 Y:1983 | 04 | 1983 | REPAIR AND ELIMINATE STEAM LEAKS | $2,438 | $1,127 | Implemented |
OK0094 # 06 Y:1983 | 06 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $263 | $200 | Implemented |
OK0094 # 08 Y:1983 | 08 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $156 | $47 | Implemented |
OK0094 # 09 Y:1983 | 09 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $87 | $51 | Implemented |
UD0081 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $424 | $341 | Implemented |
UD0081 # 02 Y:1983 | 02 | 1983 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,911 | $0 | Implemented |
UD0081 # 03 Y:1983 | 03 | 1983 | INSULATE BARE EQUIPMENT | $3,417 | $188 | Implemented |
TN0165 # 03 Y:1982 | 03 | 1982 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,132 | $200 | Implemented |
TN0165 # 04 Y:1982 | 04 | 1982 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,920 | $500 | Implemented |