Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
92
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0215 # 06 Y:2023 | 06 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,033 | $38,000 | Not Implemented |
DL0215 # 05 Y:2023 | 05 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $131,800 | $250,000 | Not Implemented |
DL0215 # 04 Y:2023 | 04 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $17,640 | $3,000 | Implemented |
DL0215 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $222,700 | $184,000 | Implemented |
DL0215 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $125,900 | $30,000 | Not Implemented |
DL0215 # 01 Y:2023 | 01 | 2023 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $29,690 | $0 | Not Implemented |
DL0215 # 07 Y:2023 | 07 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $11,998 | $52,900 | Not Implemented |
DL0133 # 04 Y:2014 | 04 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $7,800 | $6,000 | Not Implemented |
DL0133 # 10 Y:2014 | 10 | 2014 | REDUCE VENTILATION AIR | $182 | $235 | Not Implemented |
DL0133 # 09 Y:2014 | 09 | 2014 | REDUCE VENTILATION AIR | $1,110 | $0 | Not Implemented |
DL0133 # 08 Y:2014 | 08 | 2014 | RECOVER AND REUSE COOLING WATER | $5,180 | $15,600 | Not Implemented |
DL0133 # 07 Y:2014 | 07 | 2014 | INSTALL AUTOMATIC STACK DAMPER | $3,680 | $550 | Not Implemented |
DL0133 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,710 | $26,460 | Not Implemented |
DL0133 # 05 Y:2014 | 05 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,170 | $4,000 | Not Implemented |
DL0133 # 03 Y:2014 | 03 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,385 | $0 | Not Implemented |
DL0133 # 02 Y:2014 | 02 | 2014 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,540 | $18,000 | Not Implemented |
DL0133 # 01 Y:2014 | 01 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $63,690 | $134,000 | Not Implemented |
WV0459 # 03 Y:2012 | 03 | 2012 | USE RADIANT HEATER FOR SPOT HEATING | $15,798 | $23,822 | Not Implemented |
WV0459 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36,973 | $50,244 | Not Implemented |
WV0459 # 05 Y:2012 | 05 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $10,943 | $1,000 | Implemented |
WV0459 # 02 Y:2012 | 02 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $35,104 | $17,900 | Not Implemented |
WV0459 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,273 | $90 | Implemented |
WV0459 # 13 Y:2012 | 13 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $768 | $1,188 | Not Implemented |
WV0459 # 04 Y:2012 | 04 | 2012 | INSULATE BARE EQUIPMENT | $12,749 | $12,121 | Not Implemented |
WV0459 # 06 Y:2012 | 06 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $10,718 | $2,889 | Implemented |