Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
13,476
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NL0012 # 01 Y:2017 | 01 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,477 | $136 | Implemented |
NL0012 # 02 Y:2017 | 02 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,200 | $0 | Not Implemented |
NL0012 # 03 Y:2017 | 03 | 2017 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,183 | $250 | Implemented |
NL0012 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,638 | $9,825 | Implemented |
NL0012 # 05 Y:2017 | 05 | 2017 | INSTALL OCCUPANCY SENSORS | $920 | $980 | Not Implemented |
NL0012 # 06 Y:2017 | 06 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $582 | $2,100 | Not Implemented |
NL0012 # 07 Y:2017 | 07 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $163 | $157 | Implemented |
IC0196 # 01 Y:2017 | 01 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $15,797 | $22,558 | Implemented |
IC0196 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,243 | $13,967 | Implemented |
IC0196 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,963 | $1,299 | Implemented |
IC0196 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $182 | $273 | Implemented |
IC0196 # 05 Y:2017 | 05 | 2017 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $9,350 | $2,000 | Not Implemented |
IC0196 # 06 Y:2017 | 06 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,838 | $1,500 | Not Implemented |
IC0196 # 07 Y:2017 | 07 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $323 | $100 | Not Implemented |
IC0196 # 08 Y:2017 | 08 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,319 | $875 | Not Implemented |
IC0196 # 09 Y:2017 | 09 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,355 | $500 | Not Implemented |
UU0122 # 01 Y:2017 | 01 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $204,798 | $0 | Not Implemented |
UU0122 # 02 Y:2017 | 02 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $55,559 | $500 | Implemented |
UU0122 # 03 Y:2017 | 03 | 2017 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $15,162 | $26,440 | Not Implemented |
UU0122 # 04 Y:2017 | 04 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $7,349 | $800 | Implemented |
UU0122 # 05 Y:2017 | 05 | 2017 | INSTALL OCCUPANCY SENSORS | $6,799 | $4,244 | Implemented |
UU0122 # 06 Y:2017 | 06 | 2017 | INSULATE BARE EQUIPMENT | $5,324 | $11,240 | Not Implemented |
UU0122 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,745 | $0 | Not Implemented |
BS0103 # 01 Y:2017 | 01 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $181 | $74 | Not Implemented |
BS0103 # 02 Y:2017 | 02 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $172 | $60 | Not Implemented |