IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

247

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TA0112 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $730 $755 Not Implemented
TA0112 # 05 Y:2006 05 2006 INSULATE BARE EQUIPMENT $17,967 $1,359 Not Implemented
OK0722 # 01 Y:2006 01 2006 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $5,766 $10,375 Not Implemented
OK0722 # 02 Y:2006 02 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,201 $5,750 Not Implemented
OK0722 # 03 Y:2006 03 2006 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $266 $521 Implemented
OK0722 # 04 Y:2006 04 2006 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,193 $40 Implemented
OK0722 # 05 Y:2006 05 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $407 $1,300 Not Implemented
OK0722 # 06 Y:2006 06 2006 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $2,157 $15,330 Not Implemented
OK0722 # 07 Y:2006 07 2006 INSTALL OCCUPANCY SENSORS $1,066 $1,600 Not Implemented
OK0722 # 08 Y:2006 08 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,222 $67,616 Implemented
OK0722 # 09 Y:2006 09 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,795 $8,054 Implemented
WI0508 # 01 Y:2006 01 2006 $147,000 $0 Not Implemented
WI0508 # 02 Y:2006 02 2006 $30,404 $5,200 Not Implemented
WI0508 # 03 Y:2006 03 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,872 $0 Not Implemented
WI0508 # 04 Y:2006 04 2006 USE SYNTHETIC LUBRICANT $4,951 $0 Not Implemented
WI0508 # 05 Y:2006 05 2006 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $4,609 $2,100 Not Implemented
WI0508 # 06 Y:2006 06 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,905 $1,280 Not Implemented
WI0508 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,615 $0 Not Implemented
WI0508 # 08 Y:2006 08 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,015 $3,200 Not Implemented
WI0508 # 09 Y:2006 09 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,628 $1,773 Not Implemented
WI0508 # 10 Y:2006 10 2006 INSTALL OCCUPANCY SENSORS $1,154 $600 Not Implemented
WI0508 # 11 Y:2006 11 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $467 $156 Not Implemented
WV0332 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $26,457 $2,863 Implemented
WV0332 # 02 Y:2006 02 2006 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $14,629 $65,300 Not Implemented
WV0332 # 03 Y:2006 03 2006 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $10,110 $17,100 Not Implemented