Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
932
matching recommendationsSIC | 3081 | Unsupported Plastics Film & Sheet |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0195 # 08 Y:2023 | 08 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $1,986 | $2,700 | Implemented |
WM0195 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,997 | $1,000 | Implemented |
WM0195 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,381 | $700 | Implemented |
WM0195 # 05 Y:2023 | 05 | 2023 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,687 | $0 | Implemented |
WM0195 # 04 Y:2023 | 04 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,436 | $3,735 | Not Implemented |
WM0195 # 03 Y:2023 | 03 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $5,128 | $1,700 | Not Implemented |
WM0195 # 02 Y:2023 | 02 | 2023 | USE RADIANT HEATER FOR SPOT HEATING | $15,091 | $13,400 | Not Implemented |
WM0195 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,725 | $13,127 | Implemented |
UU0214 # 08 Y:2023 | 08 | 2023 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $23,820 | $214,625 | Not Implemented |
UU0214 # 07 Y:2023 | 07 | 2023 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $24,046 | $226,100 | Not Implemented |
UU0214 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $550 | $1,558 | Implemented |
UU0214 # 05 Y:2023 | 05 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $701 | $1,150 | Not Implemented |
UU0214 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,274 | $495 | Implemented |
UU0214 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,776 | $6,969 | Implemented |
UU0214 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,069 | $17,638 | Implemented |
UU0214 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $14,031 | $23,302 | Implemented |
DL0212 # 10 Y:2022 | 10 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,304 | $22,424 | Not Implemented |
DL0212 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $278 | $210 | Not Implemented |
DL0212 # 08 Y:2022 | 08 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,587 | $13,450 | Not Implemented |
DL0212 # 07 Y:2022 | 07 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,396 | $21,500 | Not Implemented |
DL0212 # 06 Y:2022 | 06 | 2022 | USE OPTIMUM THICKNESS INSULATION | $692 | $2,233 | Not Implemented |
DL0212 # 05 Y:2022 | 05 | 2022 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,655 | $5,200 | Not Implemented |
DL0212 # 04 Y:2022 | 04 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,199 | $6,100 | Not Implemented |
DL0212 # 03 Y:2022 | 03 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $634 | $495 | Not Implemented |
DL0212 # 02 Y:2022 | 02 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,912 | $5,000 | Not Implemented |