Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
405
matching recommendationsSIC | 3085 | Plastics Bottles |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0440 # 10 Y:2017 | 10 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $14,063 | $56,424 | Implemented |
LE0440 # 09 Y:2017 | 09 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,392 | $38,954 | Implemented |
LE0440 # 08 Y:2017 | 08 | 2017 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $86,307 | $68,000 | Implemented |
LE0440 # 04 Y:2017 | 04 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $41,418 | $13,000 | Implemented |
LE0440 # 03 Y:2017 | 03 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $21,749 | $3,000 | Implemented |
LE0440 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $97,167 | $5,000 | Implemented |
LE0440 # 01 Y:2017 | 01 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $14,163 | $17 | Implemented |
MZ0235 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $933 | $300 | Implemented |
MZ0235 # 05 Y:2017 | 05 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,640 | $1,000 | Implemented |
MZ0235 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,101 | $1,623 | Implemented |
MZ0235 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,672 | $13,565 | Implemented |
MZ0235 # 01 Y:2017 | 01 | 2017 | OPTIMIZE PLANT POWER FACTOR | $23,631 | $11,250 | Implemented |
TT0185 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $114,605 | $150,000 | Implemented |
TT0185 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $173,199 | $5,000 | Implemented |
TT0185 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,276 | $1,250 | Implemented |
TT0185 # 05 Y:2017 | 05 | 2017 | APPLY FOR INVESTMENT INCENTIVES | $2,174 | $40 | Implemented |
TT0185 # 06 Y:2017 | 06 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,425 | $1,425 | Implemented |
AM0724 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $126 | $210 | Implemented |
AM0724 # 07 Y:2017 | 07 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $235 | $200 | Implemented |
AM0724 # 05 Y:2017 | 05 | 2017 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,020 | $0 | Implemented |
AM0724 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,040 | $4,690 | Implemented |
AM0724 # 02 Y:2017 | 02 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,720 | $0 | Implemented |
OK0938 # 11 Y:2016 | 11 | 2016 | OPTIMIZE PLANT POWER FACTOR | $26,300 | $47,542 | Implemented |
OK0938 # 09 Y:2016 | 09 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,693 | $3,236 | Implemented |
OK0938 # 05 Y:2016 | 05 | 2016 | INSTALL SET-BACK TIMERS | $317 | $344 | Implemented |