Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
929
matching recommendationsSIC | 3086 | Plastics Foam Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0360 # 01 Y:2014 | 01 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $14,245 | $685 | Not Implemented |
SU0360 # 02 Y:2014 | 02 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,540 | $685 | Not Implemented |
SU0360 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,074 | $3,375 | Implemented |
SU0360 # 04 Y:2014 | 04 | 2014 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,863 | $3,874 | Not Implemented |
SU0360 # 05 Y:2014 | 05 | 2014 | UPGRADE OBSOLETE EQUIPMENT | $1,190 | $3,188 | Implemented |
SU0360 # 06 Y:2014 | 06 | 2014 | OPTIMIZE PLANT POWER FACTOR | $28,089 | $129,616 | Not Implemented |
SF0446 # 01 Y:2014 | 01 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $3,935 | $840 | Implemented |
SF0446 # 02 Y:2014 | 02 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $477 | $131 | Implemented |
SF0446 # 03 Y:2014 | 03 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,568 | $5,796 | Implemented |
SF0446 # 04 Y:2014 | 04 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,787 | $8,897 | Implemented |
SF0446 # 05 Y:2014 | 05 | 2014 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $17,849 | $58,975 | Implemented |
SF0446 # 06 Y:2014 | 06 | 2014 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $56,698 | $210,000 | Not Implemented |
SF0446 # 07 Y:2014 | 07 | 2014 | INSTALL OCCUPANCY SENSORS | $7,640 | $28,695 | Implemented |
SF0446 # 08 Y:2014 | 08 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,552 | $15,048 | Not Implemented |
UA0111 # 01 Y:2013 | 01 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,225 | $851 | Implemented |
UA0111 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42,878 | $2,530 | Implemented |
UA0111 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,637 | $100 | Implemented |
MI0250 # 01 Y:2013 | 01 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $25,326 | $3,900 | Implemented |
MI0250 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,636 | $1,660 | Implemented |
MI0250 # 03 Y:2013 | 03 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,559 | $2,200 | Implemented |
MI0250 # 04 Y:2013 | 04 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,256 | $80 | Implemented |
MI0250 # 05 Y:2013 | 05 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,052 | $2,520 | Implemented |
MI0250 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,828 | $80 | Implemented |
MI0250 # 07 Y:2013 | 07 | 2013 | INSTALL SKYLIGHTS | $2,274 | $5,665 | Implemented |
MI0250 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,852 | $5,600 | Not Implemented |