IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

837

matching recommendations
Reset
SIC 3089 Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0258 # 02 Y:2000 02 2000 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $66,333 $50,000 Implemented
SD0258 # 03 Y:2000 03 2000 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $5,169 $2,000 Implemented
SD0258 # 04 Y:2000 04 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,957 $0 Not Implemented
SD0258 # 05 Y:2000 05 2000 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS $5,453 $8,250 Not Implemented
SD0258 # 06 Y:2000 06 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,997 $12,500 Implemented
SD0258 # 07 Y:2000 07 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,732 $7,900 Implemented
SD0258 # 08 Y:2000 08 2000 AUTOMATE FINISHING PROCESS $387,150 $250,000 Not Implemented
SD0258 # 09 Y:2000 09 2000 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $32,513 $20,000 Not Implemented
SD0258 # 10 Y:2000 10 2000 INSTALL AUTOMATIC PACKING EQUIPMENT $4,528 $3,294 Implemented
SD0258 # 11 Y:2000 11 2000 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE $84,000 $40,000 Implemented
SD0258 # 12 Y:2000 12 2000 INSTALL EQUIPMENT TO MOVE PRODUCT $62,000 $20,000 n/a
SD0240 # 01 Y:2000 01 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $114,651 $214,102 Implemented
SD0240 # 02 Y:2000 02 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,067 $2,600 Implemented
SD0240 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $193 $714 Implemented
SD0240 # 04 Y:2000 04 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $52,416 $31,000 Not Implemented
SD0240 # 05 Y:2000 05 2000 OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS $6,552 $6,000 Implemented
SF0174 # 01 Y:1999 01 1999 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $10,862 $3,899 Not Implemented
SF0174 # 02 Y:1999 02 1999 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $600 $364 Implemented
SF0174 # 03 Y:1999 03 1999 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $39,185 $52,900 Not Implemented
SF0174 # 04 Y:1999 04 1999 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $588 $1,949 Implemented
SF0174 # 05 Y:1999 05 1999 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE $604 $0 Implemented
SF0174 # 06 Y:1999 06 1999 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $29,453 $34,995 Not Implemented
SF0174 # 07 Y:1999 07 1999 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,673 $0 Implemented
SF0174 # 08 Y:1999 08 1999 INSTALL EQUIPMENT TO MOVE PRODUCT $9,463 $4,000 Not Implemented
SF0174 # 09 Y:1999 09 1999 OPTIMIZE PLANT POWER FACTOR $1,062 $1,729 Not Implemented