Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,533
matching recommendationsSIC | 327 | Concrete, Gypsum, And Plaster Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DS0085 # 05 Y:1997 | 05 | 1997 | RECOVER AND REUSE WASTE MATERIAL | $6,837 | $40,000 | Not Implemented |
DS0085 # 06 Y:1997 | 06 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $20,475 | $1,320 | Not Implemented |
DS0085 # 07 Y:1997 | 07 | 1997 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $62,848 | $40,000 | Not Implemented |
KG0070 # 01 Y:1996 | 01 | 1996 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,417 | $0 | Not Implemented |
KG0070 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,060 | $4,750 | Implemented |
KG0070 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,084 | $464 | Implemented |
KG0070 # 04 Y:1996 | 04 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $2,582 | $600 | Implemented |
KG0070 # 05 Y:1996 | 05 | 1996 | REDUCE SCRAP PRODUCTION | $3,326 | $500 | Implemented |
KG0070 # 06 Y:1996 | 06 | 1996 | REDUCE SCRAP PRODUCTION | $24,864 | $5,000 | Implemented |
OD0074 # 01 Y:1996 | 01 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,986 | $800 | n/a |
OD0074 # 02 Y:1996 | 02 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $579 | $20 | n/a |
OD0074 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,247 | $1,602 | n/a |
OD0074 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $239 | $373 | n/a |
OD0074 # 05 Y:1996 | 05 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $879 | $1,495 | n/a |
OD0074 # 06 Y:1996 | 06 | 1996 | RECOVER AND REUSE WASTE MATERIAL | $104,960 | $2,400 | n/a |
OD0074 # 07 Y:1996 | 07 | 1996 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $372 | $0 | n/a |
AS0191 # 01 Y:1996 | 01 | 1996 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,786 | $2,100 | Not Implemented |
AS0191 # 02 Y:1996 | 02 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $457 | $960 | Not Implemented |
AS0191 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,267 | $0 | Implemented |
AS0191 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,678 | $420 | Implemented |
AS0191 # 05 Y:1996 | 05 | 1996 | USE SYNTHETIC LUBRICANT | $3,607 | $1,677 | Implemented |
AS0191 # 06 Y:1996 | 06 | 1996 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $18,782 | $0 | Not Implemented |
AS0191 # 07 Y:1996 | 07 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,193 | $9,357 | Implemented |
AS0191 # 08 Y:1996 | 08 | 1996 | INSTALL OCCUPANCY SENSORS | $1,427 | $3,300 | Implemented |
AS0191 # 09 Y:1996 | 09 | 1996 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $150 | $0 | Implemented |