Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsSIC | 3272 | Concrete Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0635 # 11 Y:2002 | 11 | 2002 | INSTALL SET-BACK TIMERS | $149 | $312 | Implemented |
OK0635 # 09 Y:2002 | 09 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,632 | $440 | Implemented |
OK0635 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,070 | $200 | Implemented |
OK0635 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,624 | $2,468 | Implemented |
OK0635 # 05 Y:2002 | 05 | 2002 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $7,873 | $300 | Implemented |
OK0491 # 02 Y:1996 | 02 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,329 | $30 | Implemented |
OK0491 # 07 Y:1996 | 07 | 1996 | INSTALL / REPAIR INSULATION ON STEAM LINES | $109 | $62 | Implemented |
OK0491 # 06 Y:1996 | 06 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $234 | $400 | Implemented |
OK0491 # 05 Y:1996 | 05 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $329 | $655 | Implemented |
OK0491 # 03 Y:1996 | 03 | 1996 | USE OPTIMUM THICKNESS INSULATION | $12,771 | $37,950 | Implemented |
OK0333 # 01 Y:1991 | 01 | 1991 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $7,336 | $0 | Implemented |
OK0333 # 09 Y:1991 | 09 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $574 | $1,050 | Implemented |
OK0333 # 08 Y:1991 | 08 | 1991 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $197 | $410 | Implemented |
OK0333 # 07 Y:1991 | 07 | 1991 | INSULATE FEEDWATER TANK | $41 | $66 | Implemented |
OK0333 # 06 Y:1991 | 06 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $117 | $65 | Implemented |
OK0333 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $328 | $0 | Implemented |
OK0333 # 04 Y:1991 | 04 | 1991 | USE OPTIMUM THICKNESS INSULATION | $4,914 | $9,600 | Implemented |
OK0333 # 03 Y:1991 | 03 | 1991 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,653 | $1,800 | Implemented |
OK0333 # 02 Y:1991 | 02 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $448 | $0 | Implemented |