Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10,364
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UMS004 # 02 Y:2012 | 02 | 2012 | CONVERT TO OXYFUEL BURNERS | $156,000 | $250,000 | Not Implemented |
UMS004 # 03 Y:2012 | 03 | 2012 | COVER OPEN TANKS | $41,000 | $32,000 | Not Implemented |
UMS004 # 04 Y:2012 | 04 | 2012 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $27,600 | $75,000 | Not Implemented |
UMS004 # 05 Y:2012 | 05 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,500 | $0 | Not Implemented |
UMS004 # 06 Y:2012 | 06 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $40,000 | $40,000 | Not Implemented |
UMS004 # 07 Y:2012 | 07 | 2012 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $1,300 | $0 | Not Implemented |
LE0331 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $59,232 | $1,300 | Not Implemented |
LE0331 # 02 Y:2012 | 02 | 2012 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $42,903 | $73,485 | Not Implemented |
LE0331 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36,201 | $136,500 | Not Implemented |
LE0331 # 04 Y:2012 | 04 | 2012 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $24,579 | $0 | Implemented |
LE0331 # 05 Y:2012 | 05 | 2012 | REDESIGN PROCESS | $20,100 | $0 | Implemented |
LE0331 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,156 | $12,800 | Not Implemented |
LE0331 # 07 Y:2012 | 07 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,134 | $2,500 | Implemented |
LE0331 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,005 | $1,000 | Implemented |
LE0331 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $805 | $125 | Not Implemented |
SU0315 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,327 | $0 | Not Implemented |
SU0315 # 02 Y:2012 | 02 | 2012 | RECOVER AND REUSE SPENT ACID BATHS | $28,847 | $792 | Not Implemented |
SU0315 # 03 Y:2012 | 03 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,269 | $1,357 | Not Implemented |
SU0315 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $317 | $140 | Not Implemented |
SU0315 # 05 Y:2012 | 05 | 2012 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $149 | $652 | Not Implemented |
SU0315 # 06 Y:2012 | 06 | 2012 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $33,502 | $167,290 | Not Implemented |
SU0315 # 07 Y:2012 | 07 | 2012 | OPTIMIZE PLANT POWER FACTOR | $8,366 | $42,403 | Not Implemented |
SU0315 # 08 Y:2012 | 08 | 2012 | UPGRADE OBSOLETE EQUIPMENT | $82 | $436 | Not Implemented |
OK0819 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,728 | $10,884 | Not Implemented |
OK0819 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,891 | $16,296 | Not Implemented |