Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
360
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0253 # 05 Y:1995 | 05 | 1995 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,170 | $0 | Implemented |
AM0253 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,250 | $1,000 | Implemented |
AM0253 # 01 Y:1995 | 01 | 1995 | OPTIMIZE PLANT POWER FACTOR | $35,300 | $92,500 | Implemented |
AM0253 # 04 Y:1995 | 04 | 1995 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,860 | $5,720 | Implemented |
AM0253 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,500 | $3,000 | Implemented |
AM0253 # 06 Y:1995 | 06 | 1995 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $727 | $95 | Implemented |
OR0251 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,007 | $9,588 | Implemented |
OR0251 # 03 Y:1995 | 03 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,652 | $17,025 | Not Implemented |
OR0251 # 04 Y:1995 | 04 | 1995 | INSTALL WASTE HEAT BOILER TO PROVIDE DIRECT POWER | $145,120 | $1,495,000 | Not Implemented |
OR0251 # 01 Y:1995 | 01 | 1995 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $69,966 | $115,000 | Implemented |
UM0044 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,738 | $25,330 | Implemented |
UM0044 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,181 | $1,433 | Implemented |
UM0044 # 04 Y:1995 | 04 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $4,745 | $4,000 | Implemented |
UM0044 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $139 | $350 | Implemented |
MA0348 # 03 Y:1995 | 03 | 1995 | INSTALL OCCUPANCY SENSORS | $642 | $350 | Not Implemented |
MA0348 # 01 Y:1995 | 01 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $852 | $127 | Implemented |
MA0348 # 06 Y:1995 | 06 | 1995 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,710 | $385 | Not Implemented |
MA0348 # 02 Y:1995 | 02 | 1995 | USE SYNTHETIC LUBRICANT | $852 | $300 | Not Implemented |
MA0348 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,014 | $1,200 | Implemented |
MA0348 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,011 | $4,750 | Implemented |
UD0473 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,762 | $2,500 | Not Implemented |
UD0473 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,330 | $18,955 | Not Implemented |
UD0473 # 03 Y:1995 | 03 | 1995 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $5,523 | $7,500 | Not Implemented |
UD0473 # 01 Y:1995 | 01 | 1995 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,965 | $8,000 | Implemented |
AR0070 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,147 | $1,779 | Implemented |