Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

47

matching recommendations
Reset
SIC 331 Blast Furnace And Basic Steel Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0937 # 02 Y:2019 02 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,545 $4,311 Implemented
GT0937 # 03 Y:2019 03 2019 OPTIMIZE PLANT POWER FACTOR $10,618 $38,920 Not Implemented
GT0937 # 04 Y:2019 04 2019 RECOVER WASTE HEAT FROM EQUIPMENT $32,772 $100,000 Not Implemented
GT0937 # 05 Y:2019 05 2019 USE SOLAR HEAT TO MAKE ELECTRICTY $17,740 $158,500 Not Implemented
GT0937 # 01 Y:2019 01 2019 INSTALL OCCUPANCY SENSORS $1,362 $310 Implemented
UF0503 # 01 Y:2017 01 2017 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $69,770 $7,000 Not Implemented
UF0503 # 02 Y:2017 02 2017 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $12,043 $1,400 Not Implemented
UF0503 # 03 Y:2017 03 2017 IMPROVE COMBUSTION CONTROL CAPABILITY $9,797 $2,182 Not Implemented
UF0503 # 04 Y:2017 04 2017 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $4,014 $0 Not Implemented
UF0503 # 05 Y:2017 05 2017 TURN OFF EQUIPMENT WHEN NOT IN USE $3,268 $0 Not Implemented
UF0503 # 06 Y:2017 06 2017 USE CONTINUOUS EQUIPMENT WHICH RETAINS PROCESS HEATING CONVEYORS WITHIN THE HEATED CHAMBER $1,188 $0 Not Implemented
UF0502 # 01 Y:2017 01 2017 ADJUST BURNERS FOR EFFICIENT OPERATION $292,994 $0 Not Implemented
UF0502 # 03 Y:2017 03 2017 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $7,986 $0 Not Implemented
UF0502 # 02 Y:2017 02 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,062 $2,182 Not Implemented
UF0502 # 04 Y:2017 04 2017 IMPROVE COMBUSTION CONTROL CAPABILITY $2,634 $0 Not Implemented
UF0502 # 05 Y:2017 05 2017 REDESIGN PROCESS $1,490 $1,800 Not Implemented
UF0502 # 06 Y:2017 06 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,047 $57 Not Implemented
MI0296 # 07 Y:2016 07 2016 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,576 $2,520 Implemented
MI0296 # 08 Y:2016 08 2016 USE PHOTOCELL CONTROLS $1,616 $2,240 Not Implemented
MI0296 # 10 Y:2016 10 2016 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $926 $40 Implemented
MI0296 # 12 Y:2016 12 2016 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $544 $2,357 Not Implemented
MI0296 # 01 Y:2016 01 2016 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $23,090 $560 Not Implemented
MI0296 # 09 Y:2016 09 2016 MINIMIZE WATER USAGE $970 $2,200 Implemented
MI0296 # 02 Y:2016 02 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $17,090 $208 Implemented
MI0296 # 03 Y:2016 03 2016 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $14,550 $40 Implemented