Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
661
matching recommendationsSIC | 3315 | Steel Wire And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0961 # 06 Y:2017 | 06 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $831 | $3,220 | Not Implemented |
OK0961 # 07 Y:2017 | 07 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $216,378 | $7,000 | Not Implemented |
OK0961 # 08 Y:2017 | 08 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,104 | $792 | Not Implemented |
OK0961 # 09 Y:2017 | 09 | 2017 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $50,374 | $124,000 | Not Implemented |
OK0961 # 10 Y:2017 | 10 | 2017 | COVER OPEN TANKS | $27,427 | $3,900 | Not Implemented |
OK0961 # 11 Y:2017 | 11 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $44,544 | $8,817 | Not Implemented |
OK0961 # 12 Y:2017 | 12 | 2017 | REUSE RICH WHITE WATER IN OTHER APPLICATIONS | $523,580 | $500,000 | Not Implemented |
OK0961 # 13 Y:2017 | 13 | 2017 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $311,801 | $1,832,665 | Not Implemented |
OK0961 # 14 Y:2017 | 14 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $497,839 | $3,000,000 | Not Implemented |
SD0536 # 06 Y:2016 | 06 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,995 | $648 | Implemented |
SD0536 # 01 Y:2016 | 01 | 2016 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $91,093 | $350,298 | Not Implemented |
SD0536 # 02 Y:2016 | 02 | 2016 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $23,163 | $68,259 | Not Implemented |
SD0536 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,468 | $8,787 | Not Implemented |
SD0536 # 04 Y:2016 | 04 | 2016 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,259 | $11,760 | Not Implemented |
SD0536 # 05 Y:2016 | 05 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,594 | $11,180 | Not Implemented |
SD0536 # 07 Y:2016 | 07 | 2016 | USE PHOTOCELL CONTROLS | $2,367 | $3,700 | Not Implemented |
SD0536 # 08 Y:2016 | 08 | 2016 | INSULATE BARE EQUIPMENT | $1,796 | $2,742 | Implemented |
SD0536 # 09 Y:2016 | 09 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,472 | $200 | Not Implemented |
SD0536 # 10 Y:2016 | 10 | 2016 | INSTALL OCCUPANCY SENSORS | $1,296 | $3,200 | Implemented |
SD0536 # 11 Y:2016 | 11 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,278 | $1,200 | Implemented |
LE0413 # 08 Y:2016 | 08 | 2016 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,559 | $14,000 | Not Implemented |
LE0413 # 07 Y:2016 | 07 | 2016 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $13,462 | $25,000 | Implemented |
LE0413 # 06 Y:2016 | 06 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,404 | $15,000 | Implemented |
LE0413 # 05 Y:2016 | 05 | 2016 | INSTALL TIMERS AND/OR THERMOSTATS | $482 | $590 | Implemented |
LE0413 # 04 Y:2016 | 04 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $973 | $1,000 | Implemented |