Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
96
matching recommendationsSIC | 3317 | Steel Pipe And Tubes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0567 # 03 Y:2009 | 03 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,035 | $20 | Not Implemented |
AM0567 # 02 Y:2009 | 02 | 2009 | MODIFY WORKLOAD | $3,265 | $500 | Implemented |
AM0567 # 01 Y:2009 | 01 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,925 | $1,020 | Not Implemented |
AM0567 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $668 | $305 | Implemented |
AM0425 # 08 Y:2003 | 08 | 2003 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,006 | $0 | Implemented |
AM0425 # 07 Y:2003 | 07 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $13,500 | $16,800 | Implemented |
AM0425 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,700 | $650 | Implemented |
AM0425 # 05 Y:2003 | 05 | 2003 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $42,200 | $700 | Implemented |
AM0425 # 03 Y:2003 | 03 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $154,000 | $2,000 | Implemented |
AM0425 # 02 Y:2003 | 02 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $243,880 | $16,000 | Implemented |
AM0425 # 01 Y:2003 | 01 | 2003 | RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION | $1,157,000 | $0 | Not Implemented |
AM0425 # 04 Y:2003 | 04 | 2003 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $110,500 | $0 | Implemented |
AM0378 # 04 Y:2000 | 04 | 2000 | SWITCH TO A SOLVENT THAT CAN BE CLEANED AND RE-USED | $13,630 | $699 | Implemented |
AM0378 # 01 Y:2000 | 01 | 2000 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $21,982 | $6,500 | Implemented |
AM0378 # 02 Y:2000 | 02 | 2000 | OPTIMIZE PLANT POWER FACTOR | $18,650 | $39,500 | Implemented |
AM0378 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,660 | $500 | Implemented |
AM0378 # 07 Y:2000 | 07 | 2000 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $4,000 | $0 | Implemented |
AM0378 # 12 Y:2000 | 12 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $250 | Not Implemented |
AM0378 # 11 Y:2000 | 11 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,310 | $2,800 | Implemented |
AM0378 # 05 Y:2000 | 05 | 2000 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $11,000 | $1,350 | Implemented |
AM0378 # 09 Y:2000 | 09 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,450 | $0 | Implemented |
AM0378 # 06 Y:2000 | 06 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $9,638 | $0 | Not Implemented |
AM0378 # 08 Y:2000 | 08 | 2000 | SHIP HYDRAULIC OIL TO SECONDARY FUEL PROGRAM | $3,610 | $0 | Implemented |
AM0378 # 10 Y:2000 | 10 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,390 | $0 | Not Implemented |
AM0345 # 09 Y:1999 | 09 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $268 | $255 | Implemented |