Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
36
matching recommendationsSIC | 3317 | Steel Pipe And Tubes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0378 # 02 Y:2000 | 02 | 2000 | OPTIMIZE PLANT POWER FACTOR | $18,650 | $39,500 | Implemented |
AM0378 # 01 Y:2000 | 01 | 2000 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $21,982 | $6,500 | Implemented |
AM0378 # 12 Y:2000 | 12 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $250 | Not Implemented |
AM0378 # 11 Y:2000 | 11 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,310 | $2,800 | Implemented |
AM0378 # 10 Y:2000 | 10 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,390 | $0 | Not Implemented |
AM0378 # 09 Y:2000 | 09 | 2000 | $2,450 | $0 | Implemented | |
AM0378 # 08 Y:2000 | 08 | 2000 | SHIP HYDRAULIC OIL TO SECONDARY FUEL PROGRAM | $3,610 | $0 | Implemented |
AM0378 # 07 Y:2000 | 07 | 2000 | $4,000 | $0 | Implemented | |
AM0378 # 06 Y:2000 | 06 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $9,638 | $0 | Not Implemented |
AM0378 # 05 Y:2000 | 05 | 2000 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $11,000 | $1,350 | Implemented |
AM0378 # 04 Y:2000 | 04 | 2000 | SWITCH TO A SOLVENT THAT CAN BE CLEANED AND RE-USED | $13,630 | $699 | Implemented |
AM0378 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,660 | $500 | Implemented |
WV0203 # 02 Y:2000 | 02 | 2000 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,005 | $577 | Implemented |
WV0203 # 01 Y:2000 | 01 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $355 | $953 | Implemented |
WV0203 # 10 Y:2000 | 10 | 2000 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $123,125 | $120,000 | Not Implemented |
WV0203 # 12 Y:2000 | 12 | 2000 | $22,000 | $4,000 | Not Implemented | |
WV0203 # 11 Y:2000 | 11 | 2000 | $6,500 | $8,000 | Not Implemented | |
WV0203 # 08 Y:2000 | 08 | 2000 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $337 | $222 | Implemented |
WV0203 # 09 Y:2000 | 09 | 2000 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $18,899 | $3,577 | Not Implemented |
WV0203 # 03 Y:2000 | 03 | 2000 | REPAIR OR REPLACE STEAM TRAPS | $735 | $1,030 | Implemented |
WV0203 # 04 Y:2000 | 04 | 2000 | INSULATE BARE EQUIPMENT | $1,914 | $535 | Implemented |
WV0203 # 05 Y:2000 | 05 | 2000 | COVER OPEN TANKS | $3,228 | $1,336 | Implemented |
WV0203 # 06 Y:2000 | 06 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $233 | $129 | Not Implemented |
WV0203 # 07 Y:2000 | 07 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $223 | $45 | Implemented |
OK0596 # 04 Y:2000 | 04 | 2000 | REPAIR AND ELIMINATE STEAM LEAKS | $17,180 | $800 | Not Implemented |