Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
45
matching recommendationsSIC | 332 | Iron And Steel Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0216 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,351 | $454,189 | Not Implemented |
UU0216 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $40,810 | $55,030 | Not Implemented |
UU0216 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,031 | $2,025 | Not Implemented |
UU0216 # 05 Y:2023 | 05 | 2023 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $5,644 | $500 | Not Implemented |
UU0216 # 04 Y:2023 | 04 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $25,370 | $31,280 | Not Implemented |
UU0216 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $28,144 | $4,000 | Not Implemented |
UU0173 # 07 Y:2021 | 07 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $683 | $2,361 | Not Implemented |
UU0173 # 02 Y:2021 | 02 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,743 | $3,188 | Implemented |
UU0173 # 01 Y:2021 | 01 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $15,037 | $2,000 | Not Implemented |
UU0173 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,755 | $8,095 | Implemented |
UU0173 # 06 Y:2021 | 06 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,018 | $474 | Implemented |
UU0173 # 08 Y:2021 | 08 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $661 | $600 | Not Implemented |
UU0173 # 04 Y:2021 | 04 | 2021 | INSULATE BARE EQUIPMENT | $1,355 | $594 | Not Implemented |
UU0173 # 05 Y:2021 | 05 | 2021 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,292 | $1,300 | Not Implemented |
UU0120 # 03 Y:2017 | 03 | 2017 | INSULATE BARE EQUIPMENT | $32,948 | $23,006 | Not Implemented |
UU0120 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,587 | $61,481 | Implemented |
UU0120 # 04 Y:2017 | 04 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $12,184 | $800 | Implemented |
UU0120 # 01 Y:2017 | 01 | 2017 | CONVERT TO AIR ASSISTED / AIRLESS PAINT GUNS | $113,750 | $5,600 | Not Implemented |
UU0120 # 05 Y:2017 | 05 | 2017 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $6,334 | $400 | Implemented |
UU0120 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,227 | $410 | Implemented |
UU0120 # 07 Y:2017 | 07 | 2017 | INSTALL COMMON HEADER ON COMPRESSORS | $4,024 | $5,000 | Implemented |
UU0120 # 09 Y:2017 | 09 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,929 | $0 | Implemented |
UU0120 # 08 Y:2017 | 08 | 2017 | OPTIMIZE PLANT POWER FACTOR | $3,894 | $3,500 | Not Implemented |
BS0078 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,671 | $827 | Not Implemented |
BS0078 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,178 | $21,982 | Not Implemented |