Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,106
matching recommendationsSIC | 3321 | Gray And Ductile Iron Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0571 # 05 Y:1999 | 05 | 1999 | CONVERT TO AQUEOUS CLEANING SYSTEM | $18,667 | $0 | Not Implemented |
UD0571 # 06 Y:1999 | 06 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $15,800 | $0 | Not Implemented |
UD0571 # 07 Y:1999 | 07 | 1999 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $9,000 | $24,000 | Not Implemented |
UD0571 # 08 Y:1999 | 08 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,582 | $0 | Implemented |
UD0571 # 09 Y:1999 | 09 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,489 | $0 | Not Implemented |
WV0162 # 01 Y:1999 | 01 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $107,972 | $39,000 | Not Implemented |
WV0162 # 02 Y:1999 | 02 | 1999 | BURN A LESS EXPENSIVE GRADE OF FUEL | $6,113 | $4,000 | Not Implemented |
WV0162 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $317 | $20 | Implemented |
WV0162 # 04 Y:1999 | 04 | 1999 | PAY UTILITY BILLS ON TIME | $2,895 | $0 | Not Implemented |
WV0162 # 05 Y:1999 | 05 | 1999 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,295 | $1,350 | Not Implemented |
WV0162 # 06 Y:1999 | 06 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,920 | $109 | Implemented |
WV0162 # 07 Y:1999 | 07 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,780 | $36 | Implemented |
WV0162 # 08 Y:1999 | 08 | 1999 | USE SYNTHETIC LUBRICANT | $988 | $636 | Implemented |
WV0162 # 09 Y:1999 | 09 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $381 | $150 | Implemented |
WV0162 # 10 Y:1999 | 10 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $691 | $180 | Not Implemented |
WV0162 # 11 Y:1999 | 11 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $560 | $2,000 | Not Implemented |
WV0162 # 12 Y:1999 | 12 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,170 | $50 | Not Implemented |
WV0162 # 13 Y:1999 | 13 | 1999 | MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE | $20,000 | $432 | Implemented |
UD0563 # 07 Y:1999 | 07 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,212 | $9,270 | Implemented |
UD0563 # 08 Y:1999 | 08 | 1999 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,880 | $8,471 | Not Implemented |
UD0563 # 01 Y:1999 | 01 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $29,762 | $4,400 | Not Implemented |
UD0563 # 02 Y:1999 | 02 | 1999 | ELIMINATE/REDUCE AN OPERATION | $30,000 | $6,648 | Not Implemented |
UD0563 # 03 Y:1999 | 03 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $26,365 | $31,000 | Implemented |
UD0563 # 04 Y:1999 | 04 | 1999 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $20,536 | $3,000 | Not Implemented |
UD0563 # 05 Y:1999 | 05 | 1999 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $17,707 | $550 | Not Implemented |