IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

139

matching recommendations
Reset
SIC 335 Nonferrous Rolling And Drawing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MS0194 # 09 Y:2001 09 2001 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $2,041,680 $1,000,000 n/a
MS0194 # 08 Y:2001 08 2001 INSTALL TIMERS AND/OR THERMOSTATS $536 $355 Not Implemented
MS0194 # 07 Y:2001 07 2001 DISCONNECT BALLASTS $824 $1,560 Not Implemented
MS0194 # 06 Y:2001 06 2001 INSTALL TIMERS AND/OR THERMOSTATS $856 $355 Not Implemented
MS0194 # 05 Y:2001 05 2001 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,241 $2,240 Not Implemented
MS0194 # 04 Y:2001 04 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,507 $28,607 n/a
MS0194 # 03 Y:2001 03 2001 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT $26,678 $32,890 n/a
MS0194 # 02 Y:2001 02 2001 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $75,156 $10,000 n/a
MS0194 # 01 Y:2001 01 2001 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $110,856 $4,050 Not Implemented
MS0194 # 10 Y:2001 10 2001 INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM $120,000 $96,000 n/a
MS0195 # 01 Y:2001 01 2001 RECOVER WASTE HEAT FROM EQUIPMENT $5,968 $1,701 Not Implemented
MS0195 # 02 Y:2001 02 2001 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,494 $1,000 Implemented
MS0195 # 03 Y:2001 03 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,150 $7,965 Not Implemented
MS0195 # 04 Y:2001 04 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,088 $51 Not Implemented
MS0195 # 05 Y:2001 05 2001 INSTALL TIMERS AND/OR THERMOSTATS $74 $119 Implemented
AS0314 # 01 Y:2001 01 2001 INSTALL SKYLIGHTS $474 $996 Implemented
AS0314 # 04 Y:2001 04 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $538 $30 Implemented
AS0314 # 10 Y:2001 10 2001 INSTALL EQUIPMENT TO MOVE PRODUCT $74,880 $1,732 Not Implemented
AS0314 # 06 Y:2001 06 2001 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $142 $50 Implemented
AS0314 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $256 $751 Implemented
AS0314 # 07 Y:2001 07 2001 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $11,340 $1,262 Implemented
AS0314 # 09 Y:2001 09 2001 CLEAR AND RENT EXISTING SPACE $38,822 $4,156 Implemented
AS0314 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,375 $112 Implemented
AS0314 # 05 Y:2001 05 2001 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $283 $766 Not Implemented
AS0314 # 08 Y:2001 08 2001 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $1,055 $40 Implemented