Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
139
matching recommendationsSIC | 335 | Nonferrous Rolling And Drawing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0194 # 09 Y:2001 | 09 | 2001 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $2,041,680 | $1,000,000 | n/a |
MS0194 # 08 Y:2001 | 08 | 2001 | INSTALL TIMERS AND/OR THERMOSTATS | $536 | $355 | Not Implemented |
MS0194 # 07 Y:2001 | 07 | 2001 | DISCONNECT BALLASTS | $824 | $1,560 | Not Implemented |
MS0194 # 06 Y:2001 | 06 | 2001 | INSTALL TIMERS AND/OR THERMOSTATS | $856 | $355 | Not Implemented |
MS0194 # 05 Y:2001 | 05 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,241 | $2,240 | Not Implemented |
MS0194 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,507 | $28,607 | n/a |
MS0194 # 03 Y:2001 | 03 | 2001 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $26,678 | $32,890 | n/a |
MS0194 # 02 Y:2001 | 02 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $75,156 | $10,000 | n/a |
MS0194 # 01 Y:2001 | 01 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $110,856 | $4,050 | Not Implemented |
MS0194 # 10 Y:2001 | 10 | 2001 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $120,000 | $96,000 | n/a |
MS0195 # 01 Y:2001 | 01 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,968 | $1,701 | Not Implemented |
MS0195 # 02 Y:2001 | 02 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,494 | $1,000 | Implemented |
MS0195 # 03 Y:2001 | 03 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,150 | $7,965 | Not Implemented |
MS0195 # 04 Y:2001 | 04 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,088 | $51 | Not Implemented |
MS0195 # 05 Y:2001 | 05 | 2001 | INSTALL TIMERS AND/OR THERMOSTATS | $74 | $119 | Implemented |
AS0314 # 01 Y:2001 | 01 | 2001 | INSTALL SKYLIGHTS | $474 | $996 | Implemented |
AS0314 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $538 | $30 | Implemented |
AS0314 # 10 Y:2001 | 10 | 2001 | INSTALL EQUIPMENT TO MOVE PRODUCT | $74,880 | $1,732 | Not Implemented |
AS0314 # 06 Y:2001 | 06 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $142 | $50 | Implemented |
AS0314 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $256 | $751 | Implemented |
AS0314 # 07 Y:2001 | 07 | 2001 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,340 | $1,262 | Implemented |
AS0314 # 09 Y:2001 | 09 | 2001 | CLEAR AND RENT EXISTING SPACE | $38,822 | $4,156 | Implemented |
AS0314 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,375 | $112 | Implemented |
AS0314 # 05 Y:2001 | 05 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $283 | $766 | Not Implemented |
AS0314 # 08 Y:2001 | 08 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $1,055 | $40 | Implemented |