Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
261
matching recommendationsSIC | 3351 | Copper Rolling And Drawing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0154 # 04 Y:2003 | 04 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $601 | $264 | Not Implemented |
SU0154 # 05 Y:2003 | 05 | 2003 | INSTALL OCCUPANCY SENSORS | $134 | $120 | Implemented |
SU0117 # 01 Y:2001 | 01 | 2001 | ELIMINATE/REDUCE AN OPERATION | $7,264 | $8,085 | Not Implemented |
SU0117 # 02 Y:2001 | 02 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $768 | $0 | Implemented |
SU0117 # 03 Y:2001 | 03 | 2001 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $153,410 | $531,678 | Not Implemented |
SU0117 # 04 Y:2001 | 04 | 2001 | OPTIMIZE PLANT POWER FACTOR | $12,307 | $30,550 | Not Implemented |
SU0117 # 05 Y:2001 | 05 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,845 | $158 | Implemented |
SU0117 # 06 Y:2001 | 06 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,016 | $0 | Not Implemented |
SU0117 # 07 Y:2001 | 07 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,888 | $20,600 | Implemented |
SD0281 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,478 | $1,400 | Implemented |
SD0281 # 02 Y:2001 | 02 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $32,897 | $60,000 | Not Implemented |
SD0281 # 03 Y:2001 | 03 | 2001 | INSTALL SKYLIGHTS | $17,602 | $37,000 | Not Implemented |
SD0281 # 04 Y:2001 | 04 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,025 | $2,250 | Not Implemented |
SD0281 # 05 Y:2001 | 05 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $21,557 | $45,000 | Not Implemented |
SD0281 # 06 Y:2001 | 06 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $465,613 | $1,000,000 | Not Implemented |
SD0281 # 07 Y:2001 | 07 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $4,190 | $15,000 | Not Implemented |
SD0281 # 08 Y:2001 | 08 | 2001 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $14,000 | $5,800 | Not Implemented |
UM0163 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,712 | $84,426 | Not Implemented |
UM0163 # 02 Y:2000 | 02 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,248 | $0 | Implemented |
UM0163 # 03 Y:2000 | 03 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,496 | $500 | Implemented |
UM0163 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,147 | $300 | Implemented |
UM0163 # 05 Y:2000 | 05 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,922 | $1,500 | Not Implemented |
UM0163 # 06 Y:2000 | 06 | 2000 | INSULATE BARE EQUIPMENT | $2,100 | $200 | Not Implemented |
UM0163 # 07 Y:2000 | 07 | 2000 | INSULATE BARE EQUIPMENT | $10,078 | $10,000 | Not Implemented |
UM0163 # 08 Y:2000 | 08 | 2000 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $14,512 | $60,000 | Not Implemented |