Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 3357 | Nonferrous Wiredrawing & Insulating |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0643 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $338 | $424 | Implemented |
SD0643 # 04 Y:2024 | 04 | 2024 | USE OPTIMUM TEMPERATURE | $6,846 | $0 | Implemented |
SD0643 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $489 | $250 | Implemented |
SF0586 # 08 Y:2022 | 08 | 2022 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $62,090 | $317,631 | Implemented |
SF0586 # 07 Y:2022 | 07 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,736 | $14,830 | Implemented |
SF0586 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $1,974 | $4,260 | Implemented |
SF0586 # 05 Y:2022 | 05 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $35,916 | $68,135 | Implemented |
SF0586 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,428 | $26,487 | Implemented |
SF0586 # 03 Y:2022 | 03 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $38,078 | $22,361 | Implemented |
SF0586 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,868 | $0 | Implemented |
SF0586 # 01 Y:2022 | 01 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,887 | $0 | Implemented |
SF0141 # 08 Y:1998 | 08 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $2,999 | $125 | Implemented |
SF0141 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $927 | $0 | Implemented |
SF0141 # 06 Y:1998 | 06 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,436 | $3,582 | Implemented |
SF0060 # 06 Y:1995 | 06 | 1995 | USE SYNTHETIC LUBRICANT | $1,512 | $732 | Implemented |
SF0060 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,429 | $1,233 | Implemented |
SF0060 # 03 Y:1995 | 03 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,582 | $18,315 | Implemented |
SF0060 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,112 | $750 | Implemented |
SF0060 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,343 | $2,320 | Implemented |
SD0012 # 01 Y:1992 | 01 | 1992 | INSULATE BARE EQUIPMENT | $6,376 | $287 | Implemented |
SD0012 # 07 Y:1992 | 07 | 1992 | KEEP LAMPS AND REFLECTORS CLEAN | $27,392 | $31,986 | Implemented |
SD0012 # 06 Y:1992 | 06 | 1992 | INSTALL SET-BACK TIMERS | $4,161 | $5,550 | Implemented |
SD0012 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $104 | $160 | Implemented |
SD0012 # 03 Y:1992 | 03 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $851 | $825 | Implemented |