Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
639
matching recommendationsSIC | 3357 | Nonferrous Wiredrawing & Insulating |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0060 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,112 | $750 | Implemented |
SF0060 # 03 Y:1995 | 03 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,582 | $18,315 | Implemented |
SF0060 # 04 Y:1995 | 04 | 1995 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $876 | $1,291 | Not Implemented |
SF0060 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,429 | $1,233 | Implemented |
SF0060 # 06 Y:1995 | 06 | 1995 | USE SYNTHETIC LUBRICANT | $1,512 | $732 | Implemented |
OD0021 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,805 | $60,851 | Implemented |
OD0021 # 02 Y:1995 | 02 | 1995 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,122 | $14,360 | Not Implemented |
OD0021 # 03 Y:1995 | 03 | 1995 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,350 | $880 | Not Implemented |
OD0021 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,240 | $800 | Implemented |
OD0021 # 05 Y:1995 | 05 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $981 | $1,736 | Implemented |
OD0021 # 06 Y:1995 | 06 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $343 | $786 | Not Implemented |
OD0021 # 07 Y:1995 | 07 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $470 | $200 | Implemented |
OD0021 # 08 Y:1995 | 08 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $10,700 | $1,758 | Not Implemented |
OK0430 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,200 | $5,400 | Implemented |
OK0430 # 02 Y:1994 | 02 | 1994 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,505 | $900 | Implemented |
OK0430 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,262 | $1,173 | Implemented |
OK0430 # 04 Y:1994 | 04 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $909 | $0 | Implemented |
OK0430 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $305 | $1,600 | Not Implemented |
OK0430 # 06 Y:1994 | 06 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $191 | $444 | Not Implemented |
OK0430 # 07 Y:1994 | 07 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $68 | $0 | Not Implemented |
KU0402 # 01 Y:1993 | 01 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $29,764 | $80,000 | Not Implemented |
KU0402 # 02 Y:1993 | 02 | 1993 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,617 | $3,517 | Implemented |
KU0402 # 03 Y:1993 | 03 | 1993 | INSTALL SET-BACK TIMERS | $3,940 | $1,000 | Implemented |
KU0402 # 04 Y:1993 | 04 | 1993 | INSTALL OCCUPANCY SENSORS | $377 | $200 | Not Implemented |
KU0402 # 05 Y:1993 | 05 | 1993 | OPERATE BOILERS ON HIGH FIRE SETTING | $3,802 | $12,100 | Not Implemented |