Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
155
matching recommendationsSIC | 339 | Miscellaneous Primary Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0460 # 07 Y:2015 | 07 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,924 | $9,629 | Not Implemented |
SF0460 # 06 Y:2015 | 06 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,269 | $9,057 | Not Implemented |
SF0460 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,462 | $9,228 | Implemented |
SF0460 # 04 Y:2015 | 04 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,945 | $2,541 | Not Implemented |
SF0460 # 03 Y:2015 | 03 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,080 | $4,429 | Not Implemented |
SF0460 # 02 Y:2015 | 02 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $5,167 | $624 | Implemented |
SF0460 # 01 Y:2015 | 01 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $14,832 | $0 | Not Implemented |
SF0444 # 05 Y:2014 | 05 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,642 | $40,100 | Not Implemented |
SF0444 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $404 | $1,967 | Implemented |
SF0444 # 03 Y:2014 | 03 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,895 | $22,758 | Not Implemented |
SF0444 # 02 Y:2014 | 02 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,108 | $4,124 | Not Implemented |
SF0444 # 01 Y:2014 | 01 | 2014 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $9,479 | $8,763 | Not Implemented |
LM0092 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,281 | $170 | Implemented |
LM0092 # 04 Y:2005 | 04 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $211 | $246 | Not Implemented |
LM0092 # 05 Y:2005 | 05 | 2005 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $62,655 | $140,000 | Implemented |
LM0092 # 06 Y:2005 | 06 | 2005 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $12,597 | $5,000 | Implemented |
LM0092 # 07 Y:2005 | 07 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $19,657 | $5,000 | Implemented |
LM0092 # 08 Y:2005 | 08 | 2005 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $36,180 | $5,000 | Implemented |
LM0092 # 09 Y:2005 | 09 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $98,438 | $100,000 | Implemented |
LM0092 # 11 Y:2005 | 11 | 2005 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $1,200 | $100 | Implemented |
LM0092 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,559 | $2,640 | Not Implemented |
LM0092 # 02 Y:2005 | 02 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,912 | $760 | Not Implemented |
LM0092 # 10 Y:2005 | 10 | 2005 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $14,473 | $100 | Implemented |
SF0289 # 06 Y:2004 | 06 | 2004 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $270 | $885 | Implemented |
SF0289 # 01 Y:2004 | 01 | 2004 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $2,527 | $2,527 | Implemented |