Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

123

matching recommendations
Reset
SIC 3398 Metal Heat Treating
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0279 # 05 Y:2004 05 2004 OPTIMIZE PLANT POWER FACTOR $1,079 $1,376 Not Implemented
LM0045 # 01 Y:2002 01 2002 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,878 $5,000 Not Implemented
LM0045 # 02 Y:2002 02 2002 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,317 $1,000 Not Implemented
LM0045 # 03 Y:2002 03 2002 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $3,903 $0 Implemented
LM0045 # 04 Y:2002 04 2002 USE EVAPORATION TO CONCENTRATE MATERIAL $3,478 $5,500 Implemented
LM0045 # 05 Y:2002 05 2002 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $37,050 $11,250 Implemented
LM0045 # 06 Y:2002 06 2002 ADVERTISE PRODUCT OR SERVICE $198,750 $2,000 Not Implemented
LM0045 # 07 Y:2002 07 2002 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $176,517 $2,000 Not Implemented
LM0037 # 01 Y:2002 01 2002 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $1,266 $1,050 Not Implemented
LM0037 # 02 Y:2002 02 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,665 $2,150 Not Implemented
LM0037 # 03 Y:2002 03 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,259 $1,700 Implemented
LM0037 # 04 Y:2002 04 2002 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $24,595 $27,000 Not Implemented
LM0037 # 05 Y:2002 05 2002 USE OPTIMUM THICKNESS INSULATION $1,908 $306 Not Implemented
LM0037 # 06 Y:2002 06 2002 INSULATE BARE EQUIPMENT $755 $224 Not Implemented
LM0037 # 07 Y:2002 07 2002 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $45,000 $40,000 Not Implemented
LM0037 # 08 Y:2002 08 2002 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $17,066 $14,227 Not Implemented
LM0020 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,625 $869 Not Implemented
LM0020 # 02 Y:2001 02 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,709 $0 Implemented
LM0020 # 03 Y:2001 03 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $81,101 $150,000 Not Implemented
LM0020 # 04 Y:2001 04 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $4,792 $11,800 Not Implemented
LM0020 # 05 Y:2001 05 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $1,575 $300 Implemented
LM0020 # 06 Y:2001 06 2001 MODIFY WORKLOAD $201,115 $1,000 Implemented
LM0020 # 07 Y:2001 07 2001 MODIFY WORKLOAD $12,653 $1,199 Not Implemented
LM0012 # 01 Y:2001 01 2001 INSTALL SKYLIGHTS $2,320 $1,700 Not Implemented
LM0012 # 02 Y:2001 02 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $9,287 $8,000 Implemented