IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

18

matching recommendations
Reset
SIC 3398 Metal Heat Treating
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IC0064 # 05 Y:2003 05 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $20,210 $85,743 Not Implemented
IC0064 # 04 Y:2003 04 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,718 $8,856 Not Implemented
IC0064 # 03 Y:2003 03 2003 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $17,626 $2,500 Not Implemented
IC0064 # 02 Y:2003 02 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $7,084 $36,178 Implemented
IC0064 # 01 Y:2003 01 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,915 $20,915 Not Implemented
IC0063 # 02 Y:2003 02 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,141 $4,800 Implemented
IC0063 # 07 Y:2003 07 2003 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $7,351 $24,365 Not Implemented
IC0063 # 06 Y:2003 06 2003 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $36,807 $250,000 Not Implemented
IC0063 # 05 Y:2003 05 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,633 $15,965 Not Implemented
IC0063 # 04 Y:2003 04 2003 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $21,835 $62,344 Not Implemented
IC0063 # 03 Y:2003 03 2003 TURN OFF EQUIPMENT WHEN NOT IN USE $5,935 $0 Implemented
IC0063 # 01 Y:2003 01 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $41,654 $50,275 Not Implemented
UM0234 # 01 Y:2003 01 2003 RECOVER WASTE HEAT FROM EQUIPMENT $71,900 $180,000 Implemented
UM0234 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $27,488 $360 Not Implemented
UM0234 # 03 Y:2003 03 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,415 $2,925 Not Implemented
UM0234 # 04 Y:2003 04 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,603 $120,000 Implemented
UM0234 # 05 Y:2003 05 2003 COVER OPEN TANKS $8,523 $2,000 Not Implemented
UM0234 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,198 $5,219 Not Implemented