Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
300
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0045 # 01 Y:1995 | 01 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $1,444 | $3,310 | Not Implemented |
MS0045 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $783 | $1,219 | Not Implemented |
MS0045 # 03 Y:1995 | 03 | 1995 | COVER OPEN TANKS | $627 | $666 | Not Implemented |
MS0045 # 04 Y:1995 | 04 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,512 | $440 | Not Implemented |
MS0045 # 05 Y:1995 | 05 | 1995 | USE SYNTHETIC LUBRICANT | $225 | $20 | Not Implemented |
MS0045 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $96 | $100 | Not Implemented |
MS0034 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $686 | $2,455 | Not Implemented |
MS0034 # 02 Y:1995 | 02 | 1995 | DISCONNECT BALLASTS | $1,005 | $200 | Implemented |
MS0034 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $407 | $321 | Implemented |
MS0034 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,696 | $3,080 | Implemented |
MS0034 # 05 Y:1995 | 05 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $818 | $730 | Implemented |
MS0034 # 06 Y:1995 | 06 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $8,484 | $21,600 | Not Implemented |
MS0034 # 07 Y:1995 | 07 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $629 | $0 | Implemented |
MS0007 # 01 Y:1994 | 01 | 1994 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $17,327 | $0 | Not Implemented |
MS0007 # 02 Y:1994 | 02 | 1994 | USE RADIANT HEATER FOR SPOT HEATING | $13,927 | $18,600 | Not Implemented |
MS0007 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,345 | $5,560 | Implemented |
MS0007 # 04 Y:1994 | 04 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,319 | $1,000 | Not Implemented |
MS0007 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $319 | $109 | Implemented |
MS0001 # 01 Y:1994 | 01 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $15,400 | $2,700 | Not Implemented |
MS0001 # 02 Y:1994 | 02 | 1994 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,346 | $1,500 | Not Implemented |
MS0001 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,885 | $10,156 | Not Implemented |
MS0001 # 04 Y:1994 | 04 | 1994 | OPTIMIZE PLANT POWER FACTOR | $4,580 | $4,500 | Not Implemented |
MS0001 # 05 Y:1994 | 05 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,165 | $3,540 | Implemented |
MS0001 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $372 | $144 | Implemented |
MS0001 # 07 Y:1994 | 07 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $124 | $33 | Implemented |