Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,208
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0540 # 02 Y:2017 | 02 | 2017 | USE EVAPORATION TO CONCENTRATE MATERIAL | $11,734 | $40,000 | Not Implemented |
WV0540 # 03 Y:2017 | 03 | 2017 | INSULATE FEEDWATER TANK | $7,035 | $3,286 | Not Implemented |
WV0540 # 04 Y:2017 | 04 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $3,005 | $3,800 | Not Implemented |
WV0540 # 05 Y:2017 | 05 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $2,223 | $6,400 | Not Implemented |
WV0540 # 06 Y:2017 | 06 | 2017 | DEVELOP A REPAIR/REPLACE POLICY | $1,394 | $635 | Implemented |
WV0540 # 07 Y:2017 | 07 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,287 | $713 | Implemented |
WV0540 # 08 Y:2017 | 08 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,154 | $5,500 | Not Implemented |
WV0540 # 09 Y:2017 | 09 | 2017 | USE EVAPORATION TO CONCENTRATE MATERIAL | $883 | $3,150 | Not Implemented |
WV0540 # 10 Y:2017 | 10 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $846 | $2,370 | Implemented |
WV0540 # 11 Y:2017 | 11 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $324 | $1,001 | Implemented |
WV0540 # 12 Y:2017 | 12 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $303 | $60 | Implemented |
WV0540 # 13 Y:2017 | 13 | 2017 | INSTALL OCCUPANCY SENSORS | $129 | $135 | Implemented |
BS0093 # 01 Y:2017 | 01 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,874 | $500 | Not Implemented |
BS0093 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $999 | $4,977 | Not Implemented |
BS0093 # 03 Y:2017 | 03 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $146 | $30 | Not Implemented |
BS0093 # 04 Y:2017 | 04 | 2017 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $58 | $590 | Not Implemented |
BS0093 # 05 Y:2017 | 05 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $203 | $628 | Not Implemented |
UA0173 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $62,936 | $136,836 | Not Implemented |
UA0173 # 02 Y:2017 | 02 | 2017 | USE PHOTOCELL CONTROLS | $5,531 | $2,748 | Implemented |
UA0173 # 03 Y:2017 | 03 | 2017 | INSTALL OCCUPANCY SENSORS | $2,924 | $880 | Implemented |
UA0173 # 04 Y:2017 | 04 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,905 | $500 | Not Implemented |
UA0173 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,474 | $5,695 | Implemented |
UA0173 # 06 Y:2017 | 06 | 2017 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $35,206 | $1,000 | Not Implemented |
UA0173 # 07 Y:2017 | 07 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $21,010 | $28,800 | Not Implemented |
UA0173 # 08 Y:2017 | 08 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,811 | $150 | Implemented |