IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20,208

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0130 # 07 Y:2014 07 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,890 $100 Implemented
IP0029 # 01 Y:2014 01 2014 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $9,363 $210 Not Implemented
IP0029 # 02 Y:2014 02 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,383 $92 Not Implemented
IP0029 # 03 Y:2014 03 2014 INSTALL OCCUPANCY SENSORS $980 $122 Not Implemented
IP0029 # 04 Y:2014 04 2014 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $82,707 $12,435 Not Implemented
IP0029 # 05 Y:2014 05 2014 INSULATE BARE EQUIPMENT $2,997 $1,104 Not Implemented
IP0029 # 06 Y:2014 06 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,419 $512 Not Implemented
IP0029 # 07 Y:2014 07 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,432 $4,014 Implemented
IP0029 # 08 Y:2014 08 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $27,953 $54,929 Implemented
MA0736 # 01 Y:2014 01 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,138 $109,865 Implemented
MA0736 # 02 Y:2014 02 2014 OPTIMIZE PLANT POWER FACTOR $14,457 $14,774 Implemented
MA0736 # 03 Y:2014 03 2014 REDUCE VENTILATION AIR $7,297 $2,550 Not Implemented
MA0736 # 04 Y:2014 04 2014 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $7,218 $4,000 Implemented
MA0736 # 05 Y:2014 05 2014 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $3,360 $500 Implemented
MA0736 # 06 Y:2014 06 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,069 $6,500 Not Implemented
MA0736 # 07 Y:2014 07 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,318 $4,000 Implemented
MA0736 # 08 Y:2014 08 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $655 $500 Not Implemented
NC0523 # 01 Y:2014 01 2014 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $156,000 $600,000 Not Implemented
NC0523 # 02 Y:2014 02 2014 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $78,330 $120,000 Not Implemented
NC0523 # 03 Y:2014 03 2014 REPLACE BOILER $58,620 $90,000 Not Implemented
NC0523 # 04 Y:2014 04 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $30,419 $146,762 Not Implemented
NC0523 # 05 Y:2014 05 2014 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $8,560 $2,500 Not Implemented
NC0523 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $944 $3,012 Implemented
NC0523 # 07 Y:2014 07 2014 INSTALL OCCUPANCY SENSORS $176 $200 Implemented
NC0523 # 08 Y:2014 08 2014 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $11,195 $20,000 Not Implemented