Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
149
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0601 # 07 Y:2013 | 07 | 2013 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $9,479 | $35,500 | Not Implemented |
OR0601 # 08 Y:2013 | 08 | 2013 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $2,164 | $8,104 | Implemented |
BS0013 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,038 | $5,639 | Implemented |
BS0013 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,210 | $20 | Implemented |
BS0013 # 03 Y:2013 | 03 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $199 | $250 | Not Implemented |
BS0013 # 04 Y:2013 | 04 | 2013 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,825 | $22,200 | Not Implemented |
BS0013 # 05 Y:2013 | 05 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $312 | $77 | Implemented |
BS0013 # 06 Y:2013 | 06 | 2013 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,270 | $360 | Not Implemented |
BS0011 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,102 | $973 | Implemented |
BS0011 # 02 Y:2012 | 02 | 2012 | REDUCE VENTILATION AIR | $4,008 | $6,725 | Implemented |
BS0011 # 03 Y:2012 | 03 | 2012 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,728 | $29,500 | Not Implemented |
BS0011 # 04 Y:2012 | 04 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,878 | $6,670 | Not Implemented |
BS0011 # 05 Y:2012 | 05 | 2012 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $8,243 | $900 | Not Implemented |
BS0011 # 06 Y:2012 | 06 | 2012 | INSTALL OCCUPANCY SENSORS | $250 | $600 | Implemented |
OR0593 # 01 Y:2012 | 01 | 2012 | USE MORE EFFICIENT ADHESIVE APPLICATORS | $72,379 | $43,800 | Not Implemented |
OR0593 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,751 | $4,751 | Implemented |
OR0593 # 03 Y:2012 | 03 | 2012 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $2,514 | $900 | Not Implemented |
OR0593 # 04 Y:2012 | 04 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $930 | $2,250 | Not Implemented |
OR0593 # 05 Y:2012 | 05 | 2012 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $8,590 | $34,684 | Not Implemented |
UW0033 # 01 Y:2010 | 01 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,132 | $0 | Not Implemented |
UW0033 # 02 Y:2010 | 02 | 2010 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $7,344 | $0 | Not Implemented |
UW0033 # 03 Y:2010 | 03 | 2010 | INSULATE BARE EQUIPMENT | $5,340 | $0 | Not Implemented |
UW0033 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $620 | $0 | Not Implemented |
UW0033 # 05 Y:2010 | 05 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $429 | $0 | Implemented |
UW0033 # 06 Y:2010 | 06 | 2010 | INSTALL OCCUPANCY SENSORS | $292 | $0 | Not Implemented |