IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,436

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LM0011 # 03 Y:2001 03 2001 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $94,292 $450 Implemented
LM0011 # 04 Y:2001 04 2001 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $5,517 $12,000 Not Implemented
LM0011 # 05 Y:2001 05 2001 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $310,000 $1,000 Implemented
SD0279 # 01 Y:2001 01 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $27,073 $1,400 Implemented
SD0279 # 02 Y:2001 02 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,923 $3,500 Not Implemented
SD0279 # 03 Y:2001 03 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $155,224 $451,000 Not Implemented
SD0279 # 04 Y:2001 04 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $46,505 $45,000 Not Implemented
SD0279 # 05 Y:2001 05 2001 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,287 $3,400 Not Implemented
SD0279 # 06 Y:2001 06 2001 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $5,667 $1,000 Implemented
SD0279 # 07 Y:2001 07 2001 ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA $36,592 $20,000 Not Implemented
SD0279 # 08 Y:2001 08 2001 RECOVER WASTE HEAT FROM EQUIPMENT $6,950 $5,000 Not Implemented
SD0279 # 09 Y:2001 09 2001 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $540 $1,500 Not Implemented
SD0279 # 10 Y:2001 10 2001 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $466,185 $5,112,000 Not Implemented
SD0279 # 11 Y:2001 11 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $10,164 $15,000 Not Implemented
SD0279 # 12 Y:2001 12 2001 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $4,500 $600 Not Implemented
SD0279 # 13 Y:2001 13 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $322,709 $20,000 Implemented
LM0004 # 01 Y:2001 01 2001 INSTALL SKYLIGHTS $8,789 $8,500 Not Implemented
LM0004 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,547 $725 Implemented
LM0004 # 03 Y:2001 03 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $910 $1,530 Not Implemented
LM0004 # 04 Y:2001 04 2001 USE DEMAND CONTROLLER OR LOAD SHEDDER $8,492 $1,950 Not Implemented
LM0004 # 05 Y:2001 05 2001 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $3,420 $1,000 Not Implemented
LM0004 # 06 Y:2001 06 2001 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $666 $1,000 Implemented
LM0004 # 07 Y:2001 07 2001 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $44,800 $1,000 Implemented
LM0004 # 08 Y:2001 08 2001 CLEAR AND RENT EXISTING SPACE $240,000 $25,000 Not Implemented
LM0003 # 01 Y:2001 01 2001 INSTALL SKYLIGHTS $1,651 $4,100 Not Implemented