Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
134
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0150 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $729 | $1,532 | Not Implemented |
NC0150 # 04 Y:1998 | 04 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $244 | $800 | Implemented |
NC0150 # 05 Y:1998 | 05 | 1998 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,244 | $4,400 | Implemented |
NC0150 # 06 Y:1998 | 06 | 1998 | USE ADSORPTION, ION EXCHANGE TO REMOVE CONTAMINANTS | $14,434 | $500 | Not Implemented |
NC0150 # 07 Y:1998 | 07 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $45,216 | $16,000 | Not Implemented |
NC0123 # 01 Y:1997 | 01 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,987 | $0 | Implemented |
NC0123 # 02 Y:1997 | 02 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $953 | $450 | Not Implemented |
NC0123 # 03 Y:1997 | 03 | 1997 | ADD AREA LIGHTING SWITCHES | $1,475 | $2,000 | Not Implemented |
NC0123 # 04 Y:1997 | 04 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $126 | $25 | Not Implemented |
NC0123 # 05 Y:1997 | 05 | 1997 | UPGRADE CONTROLS ON COMPRESSORS | $376 | $400 | Not Implemented |
NC0123 # 06 Y:1997 | 06 | 1997 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,282 | $14,319 | Not Implemented |
NC0123 # 07 Y:1997 | 07 | 1997 | REDUCE WATER USE WITH COUNTER CURRENT RINSING | $926 | $200 | Not Implemented |
NC0123 # 08 Y:1997 | 08 | 1997 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $14,528 | $12,000 | Not Implemented |
NC0123 # 09 Y:1997 | 09 | 1997 | REDUCE SCRAP PRODUCTION | $3,429 | $15,000 | Not Implemented |
NC0123 # 10 Y:1997 | 10 | 1997 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $375 | $200 | Implemented |
NC0123 # 11 Y:1997 | 11 | 1997 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $10,775 | $0 | Implemented |
NC0123 # 12 Y:1997 | 12 | 1997 | IMPROVE SPACE COMFORT CONDITIONING | $115,000 | $200,000 | Implemented |
OD0090 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $863 | $1,657 | Not Implemented |
OD0090 # 02 Y:1997 | 02 | 1997 | BURN A LESS EXPENSIVE GRADE OF FUEL | $877 | $688 | Implemented |
OD0090 # 03 Y:1997 | 03 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,082 | $0 | Not Implemented |
OD0080 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $85 | $247 | Not Implemented |
OD0080 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,090 | $150 | Implemented |
OD0080 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $758 | $320 | Implemented |
OD0080 # 04 Y:1997 | 04 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $65 | $0 | Implemented |
OD0080 # 05 Y:1997 | 05 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $563 | $210 | Implemented |