Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,139
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0208 # 03 Y:2001 | 03 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $486 | $90 | Implemented |
WV0208 # 04 Y:2001 | 04 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $633 | $340 | Implemented |
WV0208 # 05 Y:2001 | 05 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,573 | $203 | Implemented |
WV0208 # 06 Y:2001 | 06 | 2001 | INSULATE BARE EQUIPMENT | $1,754 | $138 | Implemented |
WV0208 # 07 Y:2001 | 07 | 2001 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,301 | $1,500 | Not Implemented |
WV0208 # 08 Y:2001 | 08 | 2001 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $2,538 | $5,604 | Implemented |
WV0208 # 09 Y:2001 | 09 | 2001 | RECYCLE CLEANING SOLVENT AND REUSE | $2,056 | $8,000 | Implemented |
WV0208 # 10 Y:2001 | 10 | 2001 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $2,000 | $800 | Implemented |
WV0208 # 11 Y:2001 | 11 | 2001 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $896 | $100 | Implemented |
WV0208 # 12 Y:2001 | 12 | 2001 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $20,000 | $3,000 | Not Implemented |
WV0208 # 13 Y:2001 | 13 | 2001 | EXPAND OPERATIONS INTO UNUSED SPACE | $42,527 | $36,400 | Implemented |
AM0386 # 01 Y:2001 | 01 | 2001 | OPTIMIZE PLANT POWER FACTOR | $12,670 | $18,600 | Not Implemented |
AM0386 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,650 | $500 | Not Implemented |
AM0386 # 03 Y:2001 | 03 | 2001 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,615 | $5,500 | Not Implemented |
AM0386 # 04 Y:2001 | 04 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,420 | $0 | Not Implemented |
AM0386 # 05 Y:2001 | 05 | 2001 | PAY UTILITY BILLS ON TIME | $1,258 | $0 | Not Implemented |
AM0386 # 06 Y:2001 | 06 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $520 | $0 | Not Implemented |
AM0386 # 07 Y:2001 | 07 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $220 | $215 | Not Implemented |
AM0386 # 08 Y:2001 | 08 | 2001 | USE PHOTOCELL CONTROLS | $178 | $0 | Not Implemented |
AM0386 # 09 Y:2001 | 09 | 2001 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $100 | $0 | Not Implemented |
BD0176 # 01 Y:2001 | 01 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,662 | $12,500 | Not Implemented |
BD0176 # 02 Y:2001 | 02 | 2001 | INSTALL OCCUPANCY SENSORS | $8,517 | $5,700 | Not Implemented |
BD0176 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,853 | $1,300 | Implemented |
BD0176 # 04 Y:2001 | 04 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,269 | $600 | Not Implemented |
BD0176 # 05 Y:2001 | 05 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $12,394 | $15,000 | Not Implemented |